2111 S PURDUE AVE 90025
Certificate Information: 2111 S PURDUE AVE 90025
- Application / Permit
- 23014-10000-01523
- Plan Check / Job No.
- B23LA07175
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERSION OF (E) GARAGE WITH NEW 1ST AND 2ND FLOOR ADDITION TO ADU WITH ATTACHED REC. ROOM PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/11/2024
- Issuing Office
- Current Status
- Issued on 4/11/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 5/3/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 5/15/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 1/31/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 2/6/2024 | MAHNAZ NOURHASHEMI |
| Issued | 4/11/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/23/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2023 | JASON NG |
| Sewer availability | Cleared | 5/25/2023 | JASON NG |
| Low Impact Development (LID) | Cleared | 10/31/2023 | ERNEST TSE |
| Specific Plan | Cleared | 11/2/2023 | JULISSA LOPEZ-HODOYAN |
| Roof/Waste drainage to street | Cleared | 11/16/2023 | DARIN LAM |
| Hold | Cleared | 4/22/2024 | TERESA RIVAS |
Contact Information
| Contractor | Revenant Development And Designs Inc; Lic. No.: 1112104-B | , |
| Engineer | Acciani,, Mark; Lic. No.: NA83929 | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/23/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/21/2024 | Partial Approval | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 6/10/2024 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 6/10/2024 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Partial Approval | KEVIN SARGSYAN |
| Wood Frame | 8/22/2024 | Partial Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2024 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/2/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 1/2/2025 | Partial Approval | KIRK SANDERS |
| Underground Mechanical | 1/2/2025 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 2/4/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 2/4/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 2/4/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/21/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 2/21/2025 | Approved | KIRK SANDERS |
| HVAC-Rough | 2/21/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 2/21/2025 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/26/2025 | Conditional Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 3/26/2025 | Partial Approval | KIRK SANDERS |
| Insulation | 4/16/2025 | Approved | KIRK SANDERS |
| Drywall Nailing | 4/28/2025 | Conditional Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 5/28/2025 | Approved | KIRK SANDERS |
| Shower Pan | 5/28/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 8/15/2025 | Approved | ARAM AVEDISIAN |