657 W 30TH ST 90007
Certificate Information: 657 W 30TH ST 90007
- Application / Permit
- 23014-10000-01521
- Plan Check / Job No.
- B23VN04489
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADU #2 AT REAR LOT, (N) TWO STORY DETACHED ADU (16'-0" x 91'-2") 2 OF 2
- Permit Issued
- Issued on 11/8/2023
- Issuing Office
- Current Status
- CofO Issued on 12/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | TSE MING HUANG |
| Corrections Issued | 4/18/2023 | TSE MING HUANG |
| Quality Review Completed | 4/24/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 5/4/2023 | TSE MING HUANG |
| Applicant returned to address corrections | 7/13/2023 | TSE MING HUANG |
| Applicant returned to address corrections | 9/13/2023 | TSE MING HUANG |
| Plan Check Approved | 10/26/2023 | TSE MING HUANG |
| Issued | 11/8/2023 | APPLICANT |
| CofO in Progress | 12/12/2025 | ALEJANDRO DE ARTOLA |
| No Progress | 12/13/2025 | DEROLD HAUFF |
| CofO in Progress | 12/13/2025 | DEROLD HAUFF |
| Permit Finaled | 12/16/2025 | DEROLD HAUFF |
| CofO Issued | 12/16/2025 | DEROLD HAUFF |
| Permit Finaled | 12/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 5/11/2023 | MAX LODER |
| Historic Resource Verification | Cleared | 5/11/2023 | MAX LODER |
| Historic monument | Cleared | 5/11/2023 | MAX LODER |
| Historic monument | Cleared | 5/11/2023 | MAX LODER |
| Miscellaneous | Cleared | 5/11/2023 | YINGSHI HUANG |
| ZA Case | Cleared | 5/11/2023 | YINGSHI HUANG |
| ZI | Cleared | 5/11/2023 | YINGSHI HUANG |
| Frnt yard landscape/Water mgmt | Cleared | 5/24/2023 | SPENCER WEJROWSKI |
| Redevelopment Project Area | Cleared | 5/25/2023 | YASMINE BASHIRI |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2023 | CELINA MORENO |
| Sewer availability | Cleared | 6/15/2023 | CELINA MORENO |
| Low Impact Development (LID) | Cleared | 8/24/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 8/28/2023 | ADRIAN SANCHEZ |
| Address approval | Cleared | 9/1/2023 | AMBER CAMPBELL |
| Hydrant and Access approval | Cleared | 9/14/2023 | LAVEON RIDER |
| Construction near power lines | Cleared | 9/16/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/16/2023 | RIDWAN HARDY |
| Green Code | Cleared | 9/20/2023 | TSE MING HUANG |
Contact Information
| Contractor | A M S Construction; Lic. No.: 992388-B | , |
| Contractor | Jax J C C Inc; Lic. No.: 992388-B | , |
| Engineer | Sadeghi,, Hamid M; Lic. No.: C33504 | 30941 W AGOURA RD 236 WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/17/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 5/30/2024 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Rough | 8/6/2024 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 8/8/2024 | Partial Approval | JAMES POWERS |
| METHANE-Barrier | 8/8/2024 | Partial Approval | JAMES POWERS |
| METHANE-Subgrade | 8/8/2024 | Not Ready for Inspection | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 8/13/2024 | Partial Approval | JAMES POWERS |
| METHANE-Rough | 8/13/2024 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Subgrade | 8/15/2024 | Approved | MICHAEL LEWIS |
| Pre-Inspection | 8/15/2024 | Corrections Issued | MICHAEL LEWIS |
| METHANE-Barrier | 9/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 9/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 9/13/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 9/17/2024 | No Access for Inspection | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 9/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 9/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 9/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 11/8/2024 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 11/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/25/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 12/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 12/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 12/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 12/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 12/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 12/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 12/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 12/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/24/2024 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 1/13/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Final | 3/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/24/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Final | 3/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 4/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 8/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 11/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 11/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 12/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 12/11/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/11/2025 | Approved | ALEJANDRO DE ARTOLA |