8310-8312 S HARVARD BLVD 90047
Certificate Information: 8310-8312 S HARVARD BLVD 90047
- Application / Permit
- 23014-10000-01510
- Plan Check / Job No.
- B23LA07101
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan REMOVE PORTION OF (E) SFD AND ATT. GARAGE FOR ADDITION OF (N) ADU PER LAMC 12.22 A.33(c) and (e). INCLUDES INTERIOR REMODEL TO SFD.
- Permit Issued
- Issued on 10/24/2023
- Issuing Office
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2023 | ISIS ARGUETA |
| Corrections Issued | 4/29/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 9/22/2023 | ISIS ARGUETA |
| Plan Check Approved | 10/14/2023 | MOHAMMAD ESMAILI |
| Issued | 10/24/2023 | APPLICANT |
| CofO in Progress | 2/9/2025 | JOSE MACIAS |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
| CofO Issued | 2/13/2025 | DEROLD HAUFF |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2023 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2023 | KHAING AYE |
| Sewer availability | Cleared | 6/7/2023 | KHAING AYE |
| Construction within easement | Cleared | 8/11/2023 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 8/17/2023 | KHAING AYE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/16/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 4/18/2024 | Conditional Approval | JOSE MACIAS |
| PLUMBING-Rough | 4/18/2024 | Approved | JOSE MACIAS |
| Insulation | 4/30/2024 | Partial Approval | JOSH MEISTER |
| Deputy Wood Construction | 5/1/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 5/1/2024 | Not Ready for Inspection | JOSE MACIAS |
| Deputy Wood Construction | 8/16/2024 | Conditional Approval | JOSE MACIAS |
| Deputy Wood Construction | 8/20/2024 | Conditional Approval | JOSE MACIAS |
| BUILDING-Rough-Frame | 8/30/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 8/30/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 8/30/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 8/30/2024 | Approved | JOSE MACIAS |
| Shower Pan | 8/30/2024 | Approved | JOSE MACIAS |
| Insulation | 10/1/2024 | Partial Approval | ALEX COLIN |
| HVAC-Rough | 10/2/2024 | Corrections Issued | AMIR NAZARIAN |
| Insulation | 10/2/2024 | Corrections Issued | AMIR NAZARIAN |
| Interior/Exterior Lathing | 10/2/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 10/3/2024 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 10/3/2024 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 10/3/2024 | Corrections Issued | LUIS CASTRO |
| Insulation | 10/3/2024 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 10/15/2024 | Approved | ALEX COLIN |
| Drywall Nailing | 10/15/2024 | Approved | ALEX COLIN |
| Green Building Rough | 10/15/2024 | Approved | ALEX COLIN |
| HVAC-Rough | 10/15/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 11/5/2024 | Approved | ALEX COLIN |
| Final | 1/29/2025 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 1/29/2025 | Approved | JOSE MACIAS |
| Green Building Final | 1/29/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Not Ready | JOSE MACIAS |
| Smoke Detectors | 1/29/2025 | Approved | JOSE MACIAS |
| Final | 2/7/2025 | OK to Issue CofO | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 2/7/2025 | Approved | JOSE MACIAS |