11339 W UTOPIA AVE 90230
Certificate Information: 11339 W UTOPIA AVE 90230
- Application / Permit
- 23014-10000-01509
- Plan Check / Job No.
- B23LA06681
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION TO SFD WITH NEW TWO CAR ATTACHED GARAGE.
- Permit Issued
- Issued on 5/17/2023
- Issuing Office
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | JOE VO |
| Corrections Issued | 4/18/2023 | JOE VO |
| Quality Review Completed | 4/18/2023 | GARO TELMI |
| Plan Check Approved | 5/16/2023 | JOE VO |
| Issued | 5/17/2023 | APPLICANT |
| CofO in Progress | 3/1/2024 | JESUS RODRIGUEZ |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
| CofO Issued | 3/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2023 | DINAH GARIN |
| Sewer availability | Cleared | 4/21/2023 | DINAH GARIN |
| Specific Plan | Cleared | 4/21/2023 | JIMMY VIVAR |
| Roof/Waste drainage to street | Cleared | 5/2/2023 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/7/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/13/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/17/2023 | Approved | RICHARD STEINBACH |
| Underground Mechanical | 7/17/2023 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 7/28/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 7/28/2023 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/2/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2023 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 8/2/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Insulation | 8/2/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 9/19/2023 | Not Ready for Inspection | HERBERT GIRON |
| MERV13>=Rough | 9/19/2023 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Special/Order Compliance | 9/25/2023 | Partial Inspection | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 10/4/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/13/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 10/13/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/13/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/16/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 10/16/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/16/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/16/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 10/16/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Insulation | 10/20/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 10/20/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 10/27/2023 | Conditional Approval | RICHARD STEINBACH |
| Interior/Exterior Lathing | 11/21/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| Final | 2/29/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| MERV13>=Final | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| MERV13>=Rough | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/29/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 2/29/2024 | Approved | JESUS RODRIGUEZ |