15460 W BRIARWOOD DR 91403
Certificate Information: 15460 W BRIARWOOD DR 91403
- Application / Permit
- 23014-10000-01487
- Plan Check / Job No.
- B23LA07034
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* GROUND FLOOR ADDITION TO (E) 1-STORY SFD
- Permit Issued
- Issued on 4/16/2025
- Issuing Office
- Current Status
- Issued on 4/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | VIVIAN LAO |
| Corrections Issued | 5/10/2023 | VIVIAN LAO |
| Quality Review Completed | 5/10/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/8/2023 | VIVIAN LAO |
| Plan Check Approved | 6/14/2023 | VIVIAN LAO |
| Issued | 4/16/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2023 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/23/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/23/2023 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 6/12/2023 | SERGIO VALENZUELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/9/2026 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 4/9/2026 | Not Ready for Inspection | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 4/13/2026 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 4/16/2026 | Corrections Issued | MICHAEL CORTEZ |
| Footing/Foundation/Slab | 4/17/2026 | Conditional Approval | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 5/14/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 5/14/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/14/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 5/14/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/14/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| MERV13>=Rough | 5/14/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/14/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 5/21/2026 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/21/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/21/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 6/3/2026 | Corrections Issued | MISAEL ESPARZA |
| Shower Pan | 6/3/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/5/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 6/5/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 6/5/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 6/17/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 6/17/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 6/29/2026 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/29/2026 | Partial Approval | CHRISTOPHE COCHRAN |
| Drywall Nailing | 7/2/2026 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 7/2/2026 | Approved | CHRISTOPHE COCHRAN |