3261 N INGLEDALE TER 90039
Certificate Information: 3261 N INGLEDALE TER 90039
- Application / Permit
- 23014-10000-01473
- Plan Check / Job No.
- B23LA06929
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED NEW 24 SF. ADDITION AND INTERIOR ALTERATION TO EXISTING ONE STORY SINGLE FAMILY DWELLING PER ENGINEER DETAILS
- Permit Issued
- Issued on 5/23/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | AUNG SOE |
| Corrections Issued | 4/25/2023 | AUNG SOE |
| Building Plans Picked Up | 4/27/2023 | APPLICANT |
| Applicant returned to address corrections | 5/9/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 5/11/2023 | KHUONG TRUONG |
| Issued | 5/23/2023 | APPLICANT |
| CofO in Progress | 10/23/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 10/24/2023 | DEROLD HAUFF |
| CofO Issued | 10/24/2023 | DEROLD HAUFF |
| Permit Finaled | 10/24/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/1/2023 | JEANIE LAM |
| Sewer availability | Cleared | 5/1/2023 | JEANIE LAM |
| ZI | Cleared | 5/5/2023 | MAXFIELD VERMY |
Contact Information
| Contractor | Wdg Construction Inc; Lic. No.: 1096820-B | 5459 MERIDIAN PL BONSALL, CA 92003 |
| Engineer | Quiaot,, Florentino V; Lic. No.: C38659 | 412 W 231ST ST CARSON, CA 90745 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/15/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 6/15/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Wood Frame | 6/15/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/11/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/11/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/21/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 7/21/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/25/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/25/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 7/25/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 8/4/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 8/10/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/10/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 9/13/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/13/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 9/13/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/13/2023 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/13/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 9/26/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/26/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 9/26/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/26/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 10/23/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |