9116 S STANFORD AVE 90002

Certificate Information: 9116 S STANFORD AVE 90002

Application / Permit
23014-10000-01468
Plan Check / Job No.
B23LA06907
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED ADU OVER (E) GARAGE. See Comment.
Permit Issued
Issued on 9/7/2023
Issuing Office
Metro
Current Status
Issued on 9/7/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/14/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 TSE MING HUANG
Corrections Issued 4/24/2023 TSE MING HUANG
Quality Review Completed 4/28/2023 KEN GILL
Building Plans Picked Up 5/4/2023 APPLICANT
Plan Check Approved 8/24/2023 TSE MING HUANG
Issued 9/7/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/15/2023 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 6/15/2023 KHAING AYE
Roof/Waste drainage to street Cleared 6/15/2023 KHAING AYE
Tenant Habitability Plan Cleared 7/25/2023 ISMAEL HERNANDEZ
Sewer availability Cleared 8/7/2023 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/26/2023 Corrections Issued MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 10/3/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 10/3/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Corrections Issued MICHAEL LEWIS
Underground Mechanical 8/6/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Partial Approval MICHAEL LEWIS
Green Building Rough 10/16/2024 Not Ready for Inspection MICHAEL LEWIS
Deputy Wood Construction 11/12/2024 Conditional Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 11/15/2024 Approved MICHAEL LEWIS
Insulation 11/15/2024 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 11/27/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 11/27/2024 Corrections Issued CRAIG DAVIS
Green Building Rough 11/27/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 11/27/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 11/27/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 12/13/2024 Corrections Issued MICHAEL LEWIS
HVAC-Rough 12/13/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 12/13/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/17/2024 Corrections Issued JOHN QUINTANILLA
Green Building Rough 12/17/2024 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 12/23/2024 Approved JOHN QUINTANILLA
Green Building Rough 12/23/2024 Not Ready for Inspection JOHN QUINTANILLA
Insulation 1/7/2025 Conditional Approval JOHN QUINTANILLA
Insulation 1/21/2025 Not Ready for Inspection JOHN QUINTANILLA
Insulation 3/4/2025 Approved JOHN QUINTANILLA
Drywall Nailing 3/10/2025 Approved JOHN QUINTANILLA
Green Building Rough 3/10/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 3/10/2025 Approved JOHN QUINTANILLA
HVAC-Final 12/10/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Final 1/13/2026 Not Ready for Inspection JOHN QUINTANILLA
Final 1/28/2026 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 1/28/2026 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 1/28/2026 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 1/28/2026 Approved JOHN QUINTANILLA
Final 2/5/2026 Corrections Issued JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 2/5/2026 SGSOV Approved JOHN QUINTANILLA
Final 5/20/2026 Conditional Approval JOHN QUINTANILLA