5425 W WEATHERFORD DR 90008
Certificate Information: 5425 W WEATHERFORD DR 90008
- Application / Permit
- 23014-10000-01445
- Plan Check / Job No.
- B23LA06824
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan - remodel of and addition to (e) 1-story single family dwelling w/ basement & attached carport 1 of 3
- Permit Issued
- Issued on 5/28/2024
- Issuing Office
- Current Status
- Issued on 5/28/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | KELVIN CHUONG |
| Corrections Issued | 5/11/2023 | KELVIN CHUONG |
| Quality Review Completed | 5/16/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 7/13/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 8/18/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 4/18/2024 | KELVIN CHUONG |
| Plan Check Approved | 5/28/2024 | KELVIN CHUONG |
| Issued | 5/28/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 6/29/2023 | JEANIE LAM |
| Sewer availability | Cleared | 6/29/2023 | JEANIE LAM |
| Excavation more than 5-ft deep | Cleared | 8/15/2023 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/15/2024 | KELVIN CHUONG |
| Grading Pre-Inspection | Cleared | 4/15/2024 | KELVIN CHUONG |
| Hydrant and Access approval | Cleared | 4/29/2024 | LAVEON RIDER |
Contact Information
| Contractor | Gaia Construction Inc; Lic. No.: 912485-B | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/8/2024 | Partial Inspection | ANTHONY EGSON |
| Piling/Pier/Caisson | 8/12/2024 | Partial Approval | ANTHONY EGSON |
| Piling/Pier/Caisson | 8/13/2024 | Partial Approval | ANTHONY EGSON |
| Deputy Reinf. Concrete | 8/15/2024 | Conditional Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/10/2024 | Partial Approval | ANTHONY EGSON |
| Deputy Reinf. Concrete | 9/11/2024 | Conditional Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/23/2024 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/27/2024 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 10/25/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 10/29/2024 | Approved | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 11/4/2024 | Approved | BARRY HACHE |
| PLUMBING-Rough | 11/20/2024 | Approved | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 12/2/2024 | Approved | BARRY HACHE |
| Wood Frame | 1/6/2025 | Partial Approval | LUIS CASTRO |
| Deputy Drilled-In Anchors | 2/11/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2025 | Partial Approval | LUIS CASTRO |
| Deputy Drilled-In Anchors | 4/15/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 5/8/2025 | Partial Approval | LUIS CASTRO |
| Sewer | 5/8/2025 | Partial Approval | LUIS CASTRO |
| Deputy Drilled-In Anchors | 7/14/2025 | Conditional Approval | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2025 | Partial Approval | LUIS CASTRO |
| Sewer | 9/17/2025 | Corrections Issued | RONNIE MEDINA |
| Sewer | 9/19/2025 | Approved | LUIS CASTRO |
| Underground Mechanical | 9/19/2025 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 9/22/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 9/23/2025 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 9/23/2025 | Conditional Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 9/23/2025 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 9/23/2025 | Approved | MICHAEL LEWIS |
| Deputy Wood Construction | 9/25/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Partial Approval | SABAS ALONSO |
| Insulation | 9/26/2025 | Partial Approval | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2025 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 10/8/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 10/8/2025 | Approved | LUIS CASTRO |
| Piling/Pier/Caisson | 10/8/2025 | Approved | LUIS CASTRO |
| Insulation | 10/9/2025 | Partial Approval | BRENDAN MORELLI |
| Insulation | 10/15/2025 | Partial Approval | DEVON JACKSON |
| HVAC-Rough | 10/17/2025 | Approved | REGINA MENDEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 12/4/2025 | Corrections Issued | LUIS CASTRO |
| Interior/Exterior Lathing | 12/4/2025 | Partial Approval | LUIS CASTRO |
| Interior/Exterior Lathing | 12/18/2025 | Not Ready for Inspection | ALEX COLIN |
| Shower Pan | 12/18/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 12/19/2025 | Partial Approval | ALEX COLIN |
| Shower Pan | 1/29/2026 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 2/2/2026 | Approved | LUIS CASTRO |
| Green Building Rough | 2/2/2026 | Approved | LUIS CASTRO |
| Insulation | 2/2/2026 | Partial Approval | LUIS CASTRO |
| Interior/Exterior Lathing | 2/9/2026 | Approved | LUIS CASTRO |
| Drywall Nailing | 5/6/2026 | Approved | ALEX COLIN |