1248 S CAMDEN DR 90035

Certificate Information: 1248 S CAMDEN DR 90035

Application / Permit
23014-10000-01437
Plan Check / Job No.
B23LA06765
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan 2ND STORY ADDITION; PORCH ADDITION; INTERIOR REMODEL TO EXISTING 2-STORY SINGLE FAMILY
Permit Issued
Issued on 10/12/2023
Issuing Office
Current Status
Issued on 10/12/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/15/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 KHEDER ALRAZAA
Corrections Issued 5/12/2023 KHEDER ALRAZAA
Quality Review Completed 5/19/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 8/29/2023 KHEDER ALRAZAA
Applicant returned to address corrections 10/2/2023 CRYSTEL MAALOUF
Plan Check Approved 10/3/2023 CRYSTEL MAALOUF
Issued 10/12/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/15/2023 AHMED AMARRAGY
Grading Pre-Inspection Cleared 8/11/2023 KHEDER ALRAZAA
Eng Process Fee Ord 176,300 Cleared 8/15/2023 AHMED AMARRAGY
Sewer availability Cleared 8/15/2023 AHMED AMARRAGY

Contact Information

Architect Moffitt,, Gina Gilbert; Lic. No.: NA12330       ,
Contractor Nicon Construction Co; Lic. No.: 532461-B       ,
Engineer Cox,, Steven Jeffrey; Lic. No.: C48940 130 MAGELLAN ST      THOUSAND OAKS, CA 91360
Engineer Cox,, Steven Jeffrey; Lic. No.: NA48940       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/4/2024 Conditional Approval ASHLEY THOMPSON
Footing/Foundation/Slab 6/10/2024 Approved ASHLEY THOMPSON
METHANE-Barrier 6/10/2024 Approved ASHLEY THOMPSON
METHANE-Final 6/10/2024 Approved ASHLEY THOMPSON
METHANE-Rough 6/10/2024 Approved ASHLEY THOMPSON
METHANE-Subgrade 6/10/2024 Approved ASHLEY THOMPSON
PLUMBING-Rough 8/5/2024 Approved ASHLEY THOMPSON
Special/Order Compliance 8/5/2024 Partial Inspection REGINA MENDEZ
BUILDING-Rough-Frame 8/12/2024 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 8/12/2024 Approved ASHLEY THOMPSON
Green Building Rough 8/12/2024 Not Ready for Inspection ASHLEY THOMPSON
Special/Order Compliance 8/12/2024 Partial Inspection REGINA MENDEZ
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Partial Approval ASHLEY THOMPSON
Green Building Rough 8/15/2024 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Rough 8/15/2024 Corrections Issued ASHLEY THOMPSON
Special/Order Compliance 8/15/2024 Partial Inspection REGINA MENDEZ
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Conditional Approval ARAM AVEDISIAN
HVAC-Rough 9/25/2024 Approved ARAM AVEDISIAN
Shower Pan 9/25/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 10/23/2024 Approved REGINA MENDEZ
BUILDING-Rough-Frame 10/24/2024 Corrections Issued ASHLEY THOMPSON
Green Building Rough 10/24/2024 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 10/24/2024 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 10/29/2024 Approved ASHLEY THOMPSON
Insulation 10/29/2024 Approved ASHLEY THOMPSON
Drywall Nailing 11/5/2024 Approved ASHLEY THOMPSON
ELECTRICAL-Final 2/9/2026 Approved RYAN SALAZAR
Final 2/9/2026 Corrections Issued RYAN SALAZAR
HVAC-Final 2/9/2026 Approved RYAN SALAZAR
PLUMBING-Final 2/9/2026 Approved RYAN SALAZAR