2931 S BUCKINGHAM ROAD 90016
Certificate Information: 2931 S BUCKINGHAM ROAD 90016
- Application / Permit
- 23014-10000-01426
- Plan Check / Job No.
- B23LA06686
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert (E) attached garage to be part of (E) Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/25/2023
- Issuing Office
- Current Status
- CofO Issued on 11/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2023 | EDWIN ESPIN |
| Corrections Issued | 4/12/2023 | EDWIN ESPIN |
| Plan Check Approved | 4/21/2023 | DAVID CASTILLO |
| Issued | 5/25/2023 | APPLICANT |
| CofO in Progress | 10/30/2023 | CALEB MEISTER |
| CofO Issued | 11/5/2023 | DEROLD HAUFF |
| Permit Finaled | 11/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/5/2023 | Partial Inspection | CALEB MEISTER |
| Deputy Drilled-In Anchors | 7/3/2023 | Conditional Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 7/6/2023 | Corrections Issued | CALEB MEISTER |
| Deputy Drilled-In Anchors | 7/13/2023 | Conditional Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 7/17/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 8/2/2023 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 8/17/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 8/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 9/12/2023 | Corrections Issued | JUSTIN HAWLEY |
| Deputy Wood Construction | 9/14/2023 | Conditional Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 9/25/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 9/25/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 9/25/2023 | Approved | CALEB MEISTER |
| Insulation | 9/25/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Not Ready | CALEB MEISTER |
| Final | 10/10/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Final | 10/10/2023 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 10/10/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 10/10/2023 | Approved | CALEB MEISTER |
| Final | 10/30/2023 | OK to Issue CofO | CALEB MEISTER |
| Green Building Final | 10/30/2023 | Approved | CALEB MEISTER |