4323 N GENTRY AVE 91604
Certificate Information: 4323 N GENTRY AVE 91604
- Application / Permit
- 23014-10000-01365
- Plan Check / Job No.
- B23LA06485
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan MAJOR RENOVATION AND ADDITION TO EXISITNG 1-STORY SFD TO A 2-STORY SFD WITH ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- Current Status
- CofO Issued on 5/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/10/2023 | KHEDER ALRAZAA |
| Quality Review Completed | 6/21/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 5/24/2024 | KHEDER ALRAZAA |
| Plan Check Approved | 6/20/2024 | KHEDER ALRAZAA |
| No Progress | 7/12/2024 | KHEDER ALRAZAA |
| Plan Check Approved | 7/12/2024 | KHEDER ALRAZAA |
| Issued | 7/16/2024 | APPLICANT |
| CofO in Progress | 4/13/2026 | JAVIER RAMOS JR |
| Permit Finaled | 5/11/2026 | RUBEN SALAS |
| CofO Issued | 5/11/2026 | RUBEN SALAS |
| Permit Finaled | 5/11/2026 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 8/24/2023 | STEVEN WECHSLER |
| Permit | Cleared | 8/26/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/27/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 4/23/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 4/24/2024 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 4/24/2024 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/22/2024 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/22/2024 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 11/4/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/14/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 11/19/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Sewer | 11/19/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/23/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 12/23/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Structural Steel Frame | 12/23/2024 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/16/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 1/16/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/26/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 2/26/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 2/26/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 3/10/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/13/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 3/13/2025 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 3/13/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 4/1/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/1/2025 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 4/1/2025 | Corrections Issued | JAVIER RAMOS JR |
| Drywall Nailing | 4/24/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 4/29/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 4/29/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 4/29/2025 | Partial Approval | JAVIER RAMOS JR |
| Gas Test | 1/13/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/1/2026 | Approved | JAVIER RAMOS JR |
| Final | 4/1/2026 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 4/1/2026 | Approved | JAVIER RAMOS JR |
| Green Building Final | 4/1/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 4/1/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/1/2026 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/1/2026 | SGSOV Not Ready | JAVIER RAMOS JR |
| Service/Power Release | 4/1/2026 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/1/2026 | Approved | JAVIER RAMOS JR |
| Final | 4/13/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| PLUMBING-Final | 4/13/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/13/2026 | SGSOV Approved | JAVIER RAMOS JR |