4201 N FIGUEROA ST 90065
Certificate Information: 4201 N FIGUEROA ST 90065
- Application / Permit
- 23014-10000-01356
- Plan Check / Job No.
- B23LA06423
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (8) Automobile Rental
- Work Description
- EPLAN: Change of use from Auto Sale to Car Rental, Addition and Remodel to (E) One Story Commercial Building to New Car Rental Office/Car Wash. See Comment.
- Permit Issued
- Issued on 1/31/2024
- Issuing Office
- Current Status
- CofO Issued on 2/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | TSE MING HUANG |
| Corrections Issued | 4/18/2023 | TSE MING HUANG |
| Quality Review Completed | 4/20/2023 | EUGENE BARBEAU |
| Plan Check Approved | 1/12/2024 | TSE MING HUANG |
| Issued | 1/31/2024 | APPLICANT |
| CofO in Progress | 1/13/2025 | RONALD JIMENEZ |
| CofO in Progress | 2/12/2025 | RONALD JIMENEZ |
| Permit Finaled | 2/14/2025 | ERNESTO CORRAL |
| CofO Issued | 2/14/2025 | ERNESTO CORRAL |
| Permit Finaled | 2/14/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/5/2023 | SERGIO VALENZUELA |
| Sewer availability | Cleared | 7/5/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2023 | CHRISTINA BRACO |
| "Q" conditions | Cleared | 7/13/2023 | JASON CHAN |
| Comm Cor/Mini-Mall | Cleared | 7/13/2023 | JASON CHAN |
| Comm Cor/Mini-Mall | Cleared | 7/13/2023 | JASON CHAN |
| Comm Cor/Mini-Mall | Cleared | 7/13/2023 | JASON CHAN |
| Miscellaneous | Cleared | 7/13/2023 | JASON CHAN |
| CPC | Cleared | 9/27/2023 | MICAELA TORRES-GIL |
| HPOZ | Cleared | 9/27/2023 | MICAELA TORRES-GIL |
| ZI | Cleared | 9/27/2023 | MICAELA TORRES-GIL |
| DAS Clearance | Cleared | 9/28/2023 | Sarkis Harabedian |
| Low Impact Development (LID) | Cleared | 10/17/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/18/2023 | CHRISTINA BRACO |
| Green Code | Cleared | 10/30/2023 | Sarkis Harabedian |
Contact Information
| Architect | , ; Lic. No.: C34021 | , |
| Contractor | A & B Construction; Lic. No.: 640889-B | 1365 EAST MOUNTAIN STREET GLENDALE, CA 91207 |
| Engineer | Khanjian,, Hovik J; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/22/2024 | Corrections Issued | RAMAZANALI ALMASI |
| Special/Order Compliance | 2/22/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 3/21/2024 | Conditional Approval | RAMAZANALI ALMASI |
| Masonry Wall/Backfill | 4/9/2024 | Partial Approval | RAMAZANALI ALMASI |
| Deputy Reinf. Masonry | 4/18/2024 | Conditional Approval | RAMAZANALI ALMASI |
| Masonry Wall/Backfill | 4/22/2024 | Partial Approval | RONALD JIMENEZ |
| Masonry Wall/Backfill | 4/30/2024 | Partial Approval | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 5/8/2024 | Partial Approval | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 6/13/2024 | Partial Approval | RONALD JIMENEZ |
| Footing/Foundation/Slab | 7/10/2024 | Partial Approval | RAMAZANALI ALMASI |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Partial Approval | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 8/1/2024 | Partial Approval | RAMAZANALI ALMASI |
| Deputy Wood Construction | 8/29/2024 | Conditional Approval | RAMAZANALI ALMASI |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Approved | RAMAZANALI ALMASI |
| Insulation | 8/30/2024 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 9/4/2024 | Approved | RAMAZANALI ALMASI |
| Interior/Exterior Lathing | 9/9/2024 | Approved | RONALD JIMENEZ |
| T-Bar Ceiling | 9/18/2024 | Approved | RAMAZANALI ALMASI |
| Pre-Inspection | 10/11/2024 | Partial Inspection | RAMAZANALI ALMASI |
| Structural Steel Frame | 10/21/2024 | Approved | RAMAZANALI ALMASI |
| Final | 12/9/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 12/9/2024 | Approved | RAMAZANALI ALMASI |
| Green Building Final | 12/9/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Rough | 12/9/2024 | Approved | RAMAZANALI ALMASI |
| Reinforced Masonry Frame | 12/9/2024 | Approved | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV No Gas | RAMAZANALI ALMASI |
| Smoke Detectors | 12/9/2024 | Approved | RAMAZANALI ALMASI |
| Wood Frame | 12/9/2024 | Approved | RAMAZANALI ALMASI |
| Final | 1/10/2025 | Conditional Approval | RONALD JIMENEZ |
| Green Building Final | 1/10/2025 | Approved | RONALD JIMENEZ |