6327 W 84TH PL 90045

Certificate Information: 6327 W 84TH PL 90045

Application / Permit
23014-10000-01347
Plan Check / Job No.
B23LA06377
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 15'8" X 15'2" ADDITION TO (E) SINGLE FAMILY DWELLING TO EXTEND FAMILY ROOM. WORK TO BE DONE PER ENGINEERING AND WFPP.
Permit Issued
Issued on 5/16/2023
Issuing Office
Current Status
CofO Issued on 11/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2023 APPLICANT
Assigned to Plan Check Engineer 4/7/2023 MADISON ODELL
Corrections Issued 4/8/2023 MADISON ODELL
Applicant returned to address corrections 5/4/2023 MADISON ODELL
Applicant returned to address corrections 5/12/2023 MADISON ODELL
Plan Check Approved 5/16/2023 MADISON ODELL
Issued 5/16/2023 APPLICANT
CofO in Progress 11/18/2024 MICHAEL ALLEN
Permit Finaled 11/19/2024 RICHARD STEINBACH
CofO Issued 11/19/2024 RICHARD STEINBACH
Permit Finaled 11/19/2024 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/1/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/2/2023 DARIN LAM
Specific Plan Cleared 5/3/2023 PEDRO AYALA

Contact Information

Contractor Sharp Builders Construction Inc; Lic. No.: 884884-B       ,
Engineer Gosen,, James; Lic. No.: NA43590       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/19/2023 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 5/26/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 6/1/2023 Approved HERBERT GIRON
Insulation 6/9/2023 Partial Approval KENNETH NAGLE
Wood Frame 6/9/2023 Partial Approval KENNETH NAGLE
Deputy Wood Construction 7/5/2023 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Partial Inspection HERBERT GIRON
ELECTRICAL-Rough 7/12/2023 Partial Approval HERBERT GIRON
HVAC-Rough 7/12/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 8/9/2023 Approved RICHARD STEINBACH
Insulation 8/9/2023 Approved RICHARD STEINBACH
Interior/Exterior Lathing 8/9/2023 Approved RICHARD STEINBACH
Drywall Nailing 8/16/2023 Approved RICHARD STEINBACH
Final 11/4/2024 Corrections Issued MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 11/4/2024 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 11/4/2024 Approved MICHAEL ALLEN
ELECTRICAL-Final 11/15/2024 Approved MICHAEL ALLEN
Final 11/15/2024 OK to Issue CofO MICHAEL ALLEN
HVAC-Final 11/15/2024 Approved MICHAEL ALLEN
PLUMBING-Final 11/15/2024 Approved MICHAEL ALLEN