4337 W 28TH ST 90018

Certificate Information: 4337 W 28TH ST 90018

Application / Permit
23014-10000-01334
Plan Check / Job No.
B23LA06291
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE WITH 1ST & 2ND FLOOR ADDITION TO ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 8/12/2024
Issuing Office
Metro
Current Status
Issued on 8/12/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/6/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 MAHNAZ NOURHASHEMI
Corrections Issued 4/20/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 4/27/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 5/1/2023 APPLICANT
Applicant returned to address corrections 5/31/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 6/15/2023 MAHNAZ NOURHASHEMI
Issued 8/12/2024 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/20/2023 KURT CORRAL
Address approval Cleared 5/24/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 5/24/2023 ANA SORIANO
Sewer availability Cleared 5/24/2023 ANA SORIANO
Roof/Waste drainage to street Cleared 6/6/2023 ANA SORIANO
ZI Cleared 6/21/2023 KYLE WINSTON

Contact Information

Contractor Hill Carlos; Lic. No.: 987066-B 7924 WOODMAN AVE #49      PANORAMA CITY, CA 91402
Engineer Ibarra,, Marco A; Lic. No.: C74010 16 N MARENGON AVE STE 604      PASADENA, CA 91101

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/25/2024 Corrections Issued JUSTIN HAWLEY
Footing/Foundation/Slab 11/25/2024 Not Ready for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 11/27/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Partial Approval JOAQUIN GREENOUGH
Green Building Rough 12/13/2024 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 1/28/2025 Approved JUSTIN HAWLEY
PLUMBING-Rough 4/4/2025 Approved LUIS CASTRO
Sewer 4/4/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 4/23/2025 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Approved ENRIQUE MIRELES
Green Building Rough 4/23/2025 Approved ENRIQUE MIRELES
Deputy Wood Construction 9/8/2025 Conditional Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 9/17/2025 Approved JUSTIN HAWLEY
Green Building Rough 9/17/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 9/17/2025 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 9/17/2025 Approved JUSTIN HAWLEY
Insulation 9/30/2025 Corrections Issued ALEX COLIN
Wood Frame 10/9/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 10/22/2025 Approved ALEX COLIN
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV Not Ready JUSTIN HAWLEY
Final 5/21/2026 No Access for Inspection JUSTIN HAWLEY
Drywall Nailing 5/22/2026 Approved JUSTIN HAWLEY
Final 5/22/2026 Corrections Issued JUSTIN HAWLEY
Shower Pan 5/22/2026 Approved JUSTIN HAWLEY