609 W 75TH ST 90044
Certificate Information: 609 W 75TH ST 90044
- Application / Permit
- 23014-10000-01328
- Plan Check / Job No.
- B23LA06281
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 18'-0" x 20'-0" DETACHED GARAGE WITH 15'-0" X 11'-0" ADDITION TO NEW DETACHED ACCESSORY DWELLING UNIT (477 SQ.FT) PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER WFPP.
- Permit Issued
- Issued on 6/5/2023
- Issuing Office
- Current Status
- Issued on 6/5/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 4/25/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 5/25/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 6/4/2023 | MIROOSH KHACHATOORIAN |
| Issued | 6/5/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2023 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 5/21/2023 | CHRISTOPHER ROCHA |
| "Q" conditions | Cleared | 5/24/2023 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 5/24/2023 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/25/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 8/25/2023 | Corrections Issued | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Approved | MICHAEL LEWIS |
| Sewer | 8/30/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 8/30/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 9/15/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 9/15/2023 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/6/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 10/6/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| Interior/Exterior Lathing | 10/13/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 10/13/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 10/13/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 10/20/2023 | Corrections Issued | MICHAEL LEWIS |
| Insulation | 10/20/2023 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/27/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 10/27/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 10/27/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 11/22/2023 | Approved | RONNIE MINDANAO |
| Insulation | 11/22/2023 | Approved | RONNIE MINDANAO |