15019 W HARTSOOK ST 91403
Certificate Information: 15019 W HARTSOOK ST 91403
- Application / Permit
- 23014-10000-01326
- Plan Check / Job No.
- B23LA06279
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing 1-story Garage to ADU with 2-story addition
- Permit Issued
- Issued on 6/23/2023
- Issuing Office
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | PRANITA SHAH |
| Corrections Issued | 4/19/2023 | PRANITA SHAH |
| Quality Review Completed | 4/19/2023 | GARO TELMI |
| Plan Check Approved | 6/21/2023 | PRANITA SHAH |
| Issued | 6/23/2023 | APPLICANT |
| CofO in Progress | 3/4/2024 | THOMAS FINNILA |
| Permit Finaled | 3/18/2024 | RUBEN SALAS |
| CofO Issued | 3/18/2024 | RUBEN SALAS |
| Permit Finaled | 3/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2023 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/20/2023 | CARLOS AGUILERA |
| ZI | Cleared | 4/20/2023 | RYAN LY |
| Low Impact Development (LID) | Cleared | 5/31/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/1/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Luxury House Construction Inc; Lic. No.: 1017736-B | , |
| Contractor | Smart Construction & Design; Lic. No.: 1017736-B | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/8/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 8/8/2023 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 8/14/2023 | Partial Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 8/24/2023 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 8/25/2023 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 8/25/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 8/29/2023 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 8/31/2023 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 9/21/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 9/21/2023 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 10/19/2023 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 10/19/2023 | Partial Approval | THOMAS FINNILA |
| Deputy Wood Construction | 10/26/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Gas Test | 10/30/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 10/30/2023 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 10/30/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/8/2023 | Partial Approval | JOHN COLEMAN |
| ELECTRICAL-Rough | 11/8/2023 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Partial Approval | JOHN COLEMAN |
| Rough-Elec/Plmb/HVAC | 11/8/2023 | Partial Approval | JOHN COLEMAN |
| Wood Frame | 11/8/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 11/14/2023 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/14/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 11/15/2023 | Corrections Issued | THOMAS FINNILA |
| Insulation | 11/20/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 11/20/2023 | Partial Approval | JOHN COLEMAN |
| Shower Pan | 11/20/2023 | Approved | JOHN COLEMAN |
| Wood Frame | 11/20/2023 | Approved | JOHN COLEMAN |
| Drywall Nailing | 11/27/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/27/2023 | Partial Approval | THOMAS FINNILA |
| Underground Mechanical | 12/13/2023 | Corrections Issued | THOMAS FINNILA |
| Gas Test | 12/26/2023 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 12/26/2023 | Partial Approval | THOMAS FINNILA |
| Gas Test | 12/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 12/28/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 2/6/2024 | Corrections Issued | THOMAS FINNILA |
| Final | 2/6/2024 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 2/6/2024 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 2/6/2024 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/23/2024 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 2/23/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 2/23/2024 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 2/23/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 2/23/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 2/23/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 2/23/2024 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Final | 3/1/2024 | Approved | THOMAS FINNILA |
| Final | 3/1/2024 | OK to Issue CofO | THOMAS FINNILA |
| Service/Power Release | 3/1/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 3/1/2024 | Approved | THOMAS FINNILA |