15019 W HARTSOOK ST 91403

Certificate Information: 15019 W HARTSOOK ST 91403

Application / Permit
23014-10000-01326
Plan Check / Job No.
B23LA06279
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert existing 1-story Garage to ADU with 2-story addition
Permit Issued
Issued on 6/23/2023
Issuing Office
Current Status
CofO Issued on 3/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 PRANITA SHAH
Corrections Issued 4/19/2023 PRANITA SHAH
Quality Review Completed 4/19/2023 GARO TELMI
Plan Check Approved 6/21/2023 PRANITA SHAH
Issued 6/23/2023 APPLICANT
CofO in Progress 3/4/2024 THOMAS FINNILA
Permit Finaled 3/18/2024 RUBEN SALAS
CofO Issued 3/18/2024 RUBEN SALAS
Permit Finaled 3/18/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/20/2023 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 4/20/2023 CARLOS AGUILERA
Sewer availability Cleared 4/20/2023 CARLOS AGUILERA
ZI Cleared 4/20/2023 RYAN LY
Low Impact Development (LID) Cleared 5/31/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/1/2023 CARLOS AGUILERA

Contact Information

Contractor Luxury House Construction Inc; Lic. No.: 1017736-B       ,
Contractor Smart Construction & Design; Lic. No.: 1017736-B       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/8/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/8/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 8/14/2023 Partial Approval THOMAS FINNILA
Deputy Drilled-In Anchors 8/24/2023 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 8/25/2023 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 8/25/2023 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 8/29/2023 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 8/31/2023 Approved DAVID MATSON
BUILDING-Rough-Frame 9/21/2023 Not Ready for Inspection THOMAS FINNILA
Wood Frame 9/21/2023 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Corrections Issued THOMAS FINNILA
HVAC-Rough 10/19/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 10/19/2023 Partial Approval THOMAS FINNILA
Deputy Wood Construction 10/26/2023 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Not Ready for Inspection THOMAS FINNILA
Gas Test 10/30/2023 Not Ready for Inspection THOMAS FINNILA
Rough-Elec/Plmb/HVAC 10/30/2023 Partial Approval THOMAS FINNILA
Wood Frame 10/30/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 11/8/2023 Partial Approval JOHN COLEMAN
ELECTRICAL-Rough 11/8/2023 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Partial Approval JOHN COLEMAN
Rough-Elec/Plmb/HVAC 11/8/2023 Partial Approval JOHN COLEMAN
Wood Frame 11/8/2023 Not Ready for Inspection JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Not Ready for Inspection THOMAS FINNILA
Insulation 11/14/2023 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 11/14/2023 Not Ready for Inspection THOMAS FINNILA
Shower Pan 11/15/2023 Corrections Issued THOMAS FINNILA
Insulation 11/20/2023 Approved JOHN COLEMAN
Interior/Exterior Lathing 11/20/2023 Partial Approval JOHN COLEMAN
Shower Pan 11/20/2023 Approved JOHN COLEMAN
Wood Frame 11/20/2023 Approved JOHN COLEMAN
Drywall Nailing 11/27/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 11/27/2023 Partial Approval THOMAS FINNILA
Underground Mechanical 12/13/2023 Corrections Issued THOMAS FINNILA
Gas Test 12/26/2023 Corrections Issued THOMAS FINNILA
Underground Mechanical 12/26/2023 Partial Approval THOMAS FINNILA
Gas Test 12/28/2023 Approved CHRISTOPHE COCHRAN
Underground Mechanical 12/28/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 2/6/2024 Corrections Issued THOMAS FINNILA
Final 2/6/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 2/6/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Final 2/6/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 2/23/2024 Approved THOMAS FINNILA
ELECTRICAL-Final 2/23/2024 Not Ready for Inspection THOMAS FINNILA
Final 2/23/2024 Corrections Issued THOMAS FINNILA
HVAC-Final 2/23/2024 Approved THOMAS FINNILA
PLUMBING-Final 2/23/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Approved THOMAS FINNILA
Service/Power Release 2/23/2024 Not Ready for Inspection THOMAS FINNILA
Smoke Detectors 2/23/2024 Corrections Issued THOMAS FINNILA
ELECTRICAL-Final 3/1/2024 Approved THOMAS FINNILA
Final 3/1/2024 OK to Issue CofO THOMAS FINNILA
Service/Power Release 3/1/2024 Not Ready for Inspection THOMAS FINNILA
Smoke Detectors 3/1/2024 Approved THOMAS FINNILA