2114 N ARI LANE 90049

Certificate Information: 2114 N ARI LANE 90049

Application / Permit
23014-10000-01325
Plan Check / Job No.
B23LA06275
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 1 Story 18'-5" x 28'-1"Addition to existing 2 Story Hillside Single Family Dwelling for New Suite Bedroom and New Bathroom.
Permit Issued
Issued on 7/18/2023
Issuing Office
Current Status
CofO Issued on 5/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2023 APPLICANT
Assigned to Plan Check Engineer 4/11/2023 FERNANDO FLORES
Corrections Issued 4/12/2023 FERNANDO FLORES
Applicant returned to address corrections 5/16/2023 HANS SANTIAGO
Plan Check Approved 7/6/2023 ANDREW SANTIAGO
Issued 7/18/2023 APPLICANT
CofO in Progress 5/3/2024 KEVIN SARGSYAN
Permit Finaled 5/6/2024 DANIEL ORRANTE
CofO Issued 5/6/2024 DANIEL ORRANTE
Permit Finaled 5/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/28/2023 DARIN LAM
Sewer availability Cleared 5/2/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/3/2023 DARIN LAM
Grading Pre-Inspection Cleared 5/16/2023 ANDREW SANTIAGO
"Q" conditions Cleared 7/5/2023 LOUIS ORTEGA
ZA Case Cleared 7/5/2023 LOUIS ORTEGA
ZA Case Cleared 7/5/2023 LOUIS ORTEGA
ZI Cleared 7/5/2023 LOUIS ORTEGA

Contact Information

Architect Park,, Yong Keun; Lic. No.: C24806 351 CANON DE PARAISO LN      LA CANADA FLINTRIDGE, CA 91011
Contractor K S Construction Co; Lic. No.: 545567-B       ,
Engineer Chao,, Chunching; Lic. No.: C57893 PO BOX 8422      ROWLAND HEIGHTS, CA 91748

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/12/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 10/12/2023 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 11/15/2023 Conditional Approval DANIEL ORRANTE
ELECTRICAL-Rough 11/29/2023 Approved KEVIN SARGSYAN
HVAC-Rough 11/29/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 11/29/2023 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 12/4/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 12/4/2023 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 12/6/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 12/6/2023 Not Ready for Inspection CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 1/4/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 1/8/2024 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 2/13/2024 Corrections Issued KEVIN SARGSYAN
Green Building Rough 2/13/2024 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 2/16/2024 Approved KEVIN SARGSYAN
Insulation 2/16/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Final 4/5/2024 Approved KEVIN SARGSYAN
Final 4/5/2024 Corrections Issued KEVIN SARGSYAN
Green Building Final 4/5/2024 Approved KEVIN SARGSYAN
HVAC-Final 4/5/2024 Approved KEVIN SARGSYAN
PLUMBING-Final 4/5/2024 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 4/5/2024 Approved KEVIN SARGSYAN
Final 5/2/2024 OK to Issue CofO KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Approved KEVIN SARGSYAN