4105 S LA SALLE AVE 90062

Certificate Information: 4105 S LA SALLE AVE 90062

Application / Permit
23014-10000-01308
Plan Check / Job No.
B23LA06139
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE WITH ADDITION TO DETACHED ADU AND ADD STORAGE PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 1/8/2024
Issuing Office
Metro
Current Status
CofO Issued on 11/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 CARLOS MONTES
Corrections Issued 4/25/2023 CARLOS MONTES
Quality Review Completed 4/28/2023 KEN GILL
Building Plans Picked Up 5/5/2023 APPLICANT
Applicant returned to address corrections 9/5/2023 CARLOS MONTES
Plan Check Approved 10/4/2023 CARLOS MONTES
Issued 1/8/2024 APPLICANT
CofO in Progress 11/19/2025 SABAS ALONSO
Permit Finaled 11/20/2025 DEROLD HAUFF
Permit Finaled 11/20/2025 DEROLD HAUFF
CofO Issued 11/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/13/2023 ADRIAN SANCHEZ
Low Impact Development (LID) Cleared 8/3/2023 TOMMY YIN
Eng Process Fee Ord 176,300 Cleared 8/15/2023 DAVID VO
Roof/Waste drainage to street Cleared 8/15/2023 DAVID VO
Sewer availability Cleared 8/15/2023 DAVID VO

Contact Information

Contractor Owner-Builder       ,
Engineer Yu,, Kunyoung; Lic. No.: C66880 22812 ERIEL AVE      TORRANCE, CA 90505

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/26/2024 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 4/24/2024 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 4/29/2024 Corrections Issued SABAS ALONSO
Excavation/Setback/Form/Re-Bar 5/1/2024 Partial Approval SABAS ALONSO
Special/Order Compliance 5/1/2024 Partial Inspection DAVID FEILER
Underground Mechanical 5/1/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 5/9/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/10/2024 Corrections Issued SABAS ALONSO
Deputy Wood Construction 5/16/2024 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/16/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/17/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 7/5/2024 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 7/5/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 7/9/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 7/9/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 7/16/2024 Approved SABAS ALONSO
PLUMBING-Rough 7/16/2024 Approved SABAS ALONSO
HVAC-Rough 8/23/2024 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 9/19/2024 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Corrections Issued SABAS ALONSO
Green Building Rough 9/19/2024 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 9/19/2024 Approved SABAS ALONSO
Wood Frame 9/19/2024 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Not Ready for Inspection SABAS ALONSO
Green Building Rough 9/30/2024 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Partial Approval SABAS ALONSO
HVAC-Rough 10/2/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/16/2024 Not Ready for Inspection SABAS ALONSO
Green Building Rough 10/16/2024 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 10/16/2024 Not Ready for Inspection SABAS ALONSO
Deputy Wood Construction 10/17/2024 Conditional Approval SABAS ALONSO
Interior/Exterior Lathing 10/18/2024 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 10/22/2024 Approved SABAS ALONSO
Green Building Rough 10/22/2024 Approved SABAS ALONSO
Insulation 10/25/2024 Partial Approval JOSH MEISTER
Insulation 10/29/2024 Approved SABAS ALONSO
Drywall Nailing 11/4/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 12/2/2024 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 12/17/2024 Approved ALEX COLIN
Final 6/3/2025 Corrections Issued BRENDAN MORELLI
Green Building Final 6/3/2025 No Access for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 6/3/2025 No Access for Inspection BRENDAN MORELLI
Final 7/9/2025 Corrections Issued SABAS ALONSO
Green Building Final 7/9/2025 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 7/9/2025 Not Ready for Inspection SABAS ALONSO
Final 8/20/2025 Corrections Issued BRENDAN MORELLI
Green Building Final 8/20/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 8/20/2025 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 8/20/2025 Approved BRENDAN MORELLI
Final 9/5/2025 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Approved SABAS ALONSO
Final 9/17/2025 Not Ready for Inspection SABAS ALONSO
Final 11/18/2025 OK to Issue CofO SABAS ALONSO