12611 W WELBY WAY 91606

Certificate Information: 12611 W WELBY WAY 91606

Application / Permit
23014-10000-01307
Plan Check / Job No.
B23LA06133
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) Detached Garage with addition to create 1200 SQFT ADU per Ordinance. All work per engineering
Permit Issued
Issued on 11/30/2023
Issuing Office
Metro
Current Status
Issued on 11/30/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/4/2023 APPLICANT
Assigned to Plan Check Engineer 4/10/2023 MICHAEL LANZONE
Corrections Issued 4/11/2023 MICHAEL LANZONE
Building Plans Picked Up 6/20/2023 APPLICANT
Plan Check Approved 11/30/2023 ADAM HEGAZI
Issued 11/30/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/26/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 6/26/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 6/30/2023 TINA MIRANDA
Low Impact Development (LID) Cleared 11/28/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 11/28/2023 LEE GUILBEAUX
Address approval Cleared 11/30/2023 AMBER CAMPBELL

Contact Information

Architect Hurtado,, Jesus; Lic. No.: C29969 1310 S MCDONNELL AVENUE      LOS ANGELES, CA 90022
Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/6/2023 Partial Approval JOSE AVILA
Footing/Foundation/Slab 12/11/2023 Corrections Issued JUAN VALENZUELA
Deputy Drilled-In Anchors 12/13/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 12/15/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/29/2023 Partial Approval JOSE AVILA
Deputy Wood Construction 3/8/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 3/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/20/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Wood Frame 4/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/24/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 4/24/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 4/30/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/30/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/30/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 7/8/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/12/2024 Partial Approval ROBERT GOLD
Green Building Rough 7/12/2024 Approved ROBERT GOLD
HVAC-Rough 7/12/2024 Partial Approval ROBERT GOLD
Interior/Exterior Lathing 7/12/2024 Partial Approval ROBERT GOLD
Insulation 7/24/2024 Approved OGANES TARAKHCHYAN
Shower Pan 7/24/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 7/30/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 8/2/2024 Approved OGANES TARAKHCHYAN
Underground Mechanical 8/12/2024 Approved RYAN SALAZAR
Service/Power Release 12/11/2024 Approved OGANES TARAKHCHYAN
Underground Mechanical 12/11/2024 Approved OGANES TARAKHCHYAN