5714 E BALTIMORE ST 90042
Certificate Information: 5714 E BALTIMORE ST 90042
- Application / Permit
- 23014-10000-01306
- Plan Check / Job No.
- B23LA06127
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. ATTACH (N) 2 STORY ADU TO (E) DETACHED GARAGE & ADDITION TO GARAGE ADU CHECKED PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/25/2025
- Issuing Office
- Current Status
- Issued on 2/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | SUNMIN LEE |
| Corrections Issued | 5/2/2023 | SUNMIN LEE |
| Quality Review Completed | 5/3/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/28/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 9/6/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 10/1/2024 | SUNMIN LEE |
| Plan Check Approved | 10/9/2024 | SUNMIN LEE |
| Issued | 2/25/2025 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 6/1/2023 | CASEY JENSEN |
| Address approval | Cleared | 6/8/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2023 | JEANIE LAM |
| Sewer availability | Cleared | 6/14/2023 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 6/15/2023 | ALEXANDER HELFER |
| CPC | Cleared | 3/26/2024 | MAX LODER |
| HPOZ | Cleared | 3/28/2024 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 3/28/2024 | MAX LODER |
| ZI | Cleared | 3/28/2024 | MICAELA TORRES-GIL |
| GPI Written Notices | Cleared | 5/28/2024 | SUNMIN LEE |
| GPI Written Notices | Cleared | 5/28/2024 | SUNMIN LEE |
| Grading Pre-Inspection | Cleared | 5/28/2024 | SUNMIN LEE |
| Low Impact Development (LID) | Cleared | 8/30/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/30/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Lopez Nelson Gacula; Lic. No.: 913712-B | 8551 MOODY ST CYPRESS, CA 90630 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/3/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Pre-Inspection | 3/3/2025 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/21/2025 | Corrections Issued | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 4/10/2025 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/10/2025 | Corrections Issued | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 4/16/2025 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/16/2025 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 4/28/2025 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/1/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2025 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 8/18/2025 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 11/12/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 11/12/2025 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/1/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 12/1/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 12/1/2025 | Partial Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/5/2025 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/5/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 12/5/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/11/2025 | Partial Approval | GEM DE OCAMPO |
| Insulation | 12/18/2025 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 1/20/2026 | Approved | GEM DE OCAMPO |
| Shower Pan | 1/20/2026 | Not Ready for Inspection | GEM DE OCAMPO |
| Shower Pan | 1/22/2026 | Corrections Issued | GEM DE OCAMPO |
| Shower Pan | 2/4/2026 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/10/2026 | Approved | GEM DE OCAMPO |