5624 N WILLIS AVE 91411

Certificate Information: 5624 N WILLIS AVE 91411

Application / Permit
23014-10000-01291
Plan Check / Job No.
B23LA06054
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: 1st and 2nd Floor ADDITION to 2 STORY SFD. See Comment.
Permit Issued
Issued on 8/25/2023
Issuing Office
Current Status
CofO Issued on 11/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 TSE MING HUANG
Corrections Issued 5/1/2023 TSE MING HUANG
Quality Review Completed 5/2/2023 EUGENE BARBEAU
Plan Check Approved 8/10/2023 TSE MING HUANG
Plan Check Approved 8/24/2023 TSE MING HUANG
Issued 8/25/2023 APPLICANT
CofO in Progress 10/21/2025 RYAN SALAZAR
Permit Finaled 11/4/2025 RUBEN SALAS
CofO Issued 11/4/2025 RUBEN SALAS
Permit Finaled 11/4/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/4/2023 NIKKI ZULUETA
Sewer availability Cleared 5/4/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 7/28/2023 SHAHIN KHAZEY
Roof/Waste drainage to street Cleared 7/31/2023 NIKKI ZULUETA

Contact Information

Contractor Owner-Builder       ,
Engineer Boules,, George H; Lic. No.: NA64144       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/14/2023 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 9/20/2023 Corrections Issued RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 9/26/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/25/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Not Ready for Inspection JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 11/2/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 1/22/2024 Not Ready for Inspection RYAN SALAZAR
Deputy Wood Construction 4/10/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 4/18/2024 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 4/18/2024 Approved RYAN SALAZAR
Drywall Nailing 9/5/2024 Approved RYAN SALAZAR
Final 9/5/2024 Partial Inspection RYAN SALAZAR
Footing/Foundation/Slab 9/5/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 9/5/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 9/5/2024 Approved RYAN SALAZAR
Final 7/18/2025 Corrections Issued RYAN SALAZAR
Final 10/21/2025 OK to Issue CofO RYAN SALAZAR