5624 N WILLIS AVE 91411
Certificate Information: 5624 N WILLIS AVE 91411
- Application / Permit
- 23014-10000-01291
- Plan Check / Job No.
- B23LA06054
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: 1st and 2nd Floor ADDITION to 2 STORY SFD. See Comment.
- Permit Issued
- Issued on 8/25/2023
- Issuing Office
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | TSE MING HUANG |
| Corrections Issued | 5/1/2023 | TSE MING HUANG |
| Quality Review Completed | 5/2/2023 | EUGENE BARBEAU |
| Plan Check Approved | 8/10/2023 | TSE MING HUANG |
| Plan Check Approved | 8/24/2023 | TSE MING HUANG |
| Issued | 8/25/2023 | APPLICANT |
| CofO in Progress | 10/21/2025 | RYAN SALAZAR |
| Permit Finaled | 11/4/2025 | RUBEN SALAS |
| CofO Issued | 11/4/2025 | RUBEN SALAS |
| Permit Finaled | 11/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 5/4/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 7/28/2023 | SHAHIN KHAZEY |
| Roof/Waste drainage to street | Cleared | 7/31/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boules,, George H; Lic. No.: NA64144 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/14/2023 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 9/20/2023 | Corrections Issued | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 9/26/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 11/2/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 1/22/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Deputy Wood Construction | 4/10/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 4/18/2024 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 4/18/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/5/2024 | Approved | RYAN SALAZAR |
| Final | 9/5/2024 | Partial Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 9/5/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/5/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 9/5/2024 | Approved | RYAN SALAZAR |
| Final | 7/18/2025 | Corrections Issued | RYAN SALAZAR |
| Final | 10/21/2025 | OK to Issue CofO | RYAN SALAZAR |