2548 S COOLIDGE AVE 90064

Certificate Information: 2548 S COOLIDGE AVE 90064

Application / Permit
23014-10000-01287
Plan Check / Job No.
B23LA06051
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF EXISTING GARAGE WITH AN ADDITION TO DETACHED ADU PER ORDINANCE, REMAINING PORTION OF EXISTING GARAGAE TO BE USED AS ONE CAR GARAGE
Permit Issued
Issued on 3/13/2024
Issuing Office
Current Status
CofO Issued on 5/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 CARLOS MONTES
Corrections Issued 4/25/2023 CARLOS MONTES
Quality Review Completed 4/26/2023 GARO TELMI
Applicant returned to address corrections 10/19/2023 CARLOS MONTES
Applicant returned to address corrections 2/20/2024 CARLOS MONTES
Plan Check Approved 3/13/2024 CARLOS MONTES
Issued 3/13/2024 APPLICANT
CofO in Progress 5/6/2025 WILBER ROSALES
Permit Finaled 5/17/2025 RICHARD STEINBACH
CofO Issued 5/17/2025 RICHARD STEINBACH
Permit Finaled 5/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/4/2023 DARIN LAM
Specific Plan Cleared 5/8/2023 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 5/26/2023 DARIN LAM
Sewer availability Cleared 5/26/2023 DARIN LAM
Low Impact Development (LID) Cleared 10/4/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 10/12/2023 DARIN LAM

Contact Information

Contractor Ludis Inc; Lic. No.: 1061815-B       ,
Engineer Xia,, Ji; Lic. No.: C89014 260 S LOS ROBLES AVE, STE 100      PASADENA, CA 91101

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/12/2024 Partial Inspection HERBERT GIRON
Footing/Foundation/Slab 4/18/2024 Not Ready for Inspection JESUS PINEDA
PLUMBING-Rough 4/18/2024 Partial Approval JESUS PINEDA
Deputy Drilled-In Anchors 4/22/2024 Approved JESUS PINEDA
Excavation/Setback/Form/Re-Bar 4/22/2024 Approved JESUS PINEDA
Deputy Drilled-In Anchors 5/2/2024 Approved JESUS PINEDA
Deputy Wood Construction 5/2/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Partial Approval JESUS PINEDA
Pre-Inspection 5/8/2024 Partial Inspection TEMISTOCLES CAAL
Deputy Wood Construction 5/10/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/10/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 6/24/2024 Approved SEAN HAUPT
HVAC-Final 6/24/2024 Corrections Issued SEAN HAUPT
HVAC-Rough 6/24/2024 Approved SEAN HAUPT
PLUMBING-Rough 6/24/2024 Approved SEAN HAUPT
Rough-Elec/Plmb/HVAC 6/24/2024 Not Ready for Inspection SEAN HAUPT
Sewer 6/24/2024 Approved SEAN HAUPT
Shower Pan 6/24/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 7/8/2024 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 7/16/2024 Corrections Issued JESUS PINEDA
Insulation 7/22/2024 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 7/24/2024 Approved JESUS PINEDA
Green Building Rough 7/24/2024 Approved JESUS PINEDA
Insulation 7/24/2024 Approved JESUS PINEDA
MERV13>=Rough 7/24/2024 Approved JESUS PINEDA
Drywall Nailing 7/31/2024 Corrections Issued REGINA MENDEZ
Drywall Nailing 8/2/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 8/15/2024 Approved JESUS PINEDA
Pre-Inspection 1/22/2025 Partial Inspection JESUS PINEDA
ELECTRICAL-Final 2/21/2025 Not Ready for Inspection DANIEL VERA
Pre-Inspection 4/1/2025 Partial Inspection BOBBY KEY
Gas Test 4/7/2025 Approved BOBBY KEY
PLUMBING-Final 4/7/2025 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Not Required BOBBY KEY
Service/Power Release 4/7/2025 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 4/8/2025 Corrections Issued WILBER ROSALES
ELECTRICAL-Final 4/18/2025 Corrections Issued MEL KHACHATOURIAN
Service/Power Release 4/22/2025 No Access for Inspection WILBER ROSALES
ELECTRICAL-Final 4/23/2025 Approved WILBER ROSALES
Final 4/23/2025 Corrections Issued WILBER ROSALES
HVAC-Final 4/23/2025 Approved WILBER ROSALES
Final 5/5/2025 OK to Issue CofO WILBER ROSALES
Footing/Foundation/Slab 5/5/2025 Approved WILBER ROSALES
Green Building Final 5/5/2025 Approved WILBER ROSALES
MERV13>=Final 5/5/2025 Approved WILBER ROSALES
Service/Power Release 5/5/2025 Approved WILBER ROSALES
Smoke Detectors 5/5/2025 Approved WILBER ROSALES