20949 S DENKER AVE 90501
Certificate Information: 20949 S DENKER AVE 90501
- Application / Permit
- 23014-10000-01286
- Plan Check / Job No.
- B23LA06047
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADU addition per LAMC 12.22 A.33(c) and (d) amd Storage Addition to (E) 1-Story Garage
- Permit Issued
- Issued on 7/17/2023
- Issuing Office
- Current Status
- CofO Issued on 2/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2023 | DAVID CASTILLO |
| Corrections Issued | 4/7/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 4/25/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 5/23/2023 | ARSALAN SHABESTARI |
| Issued | 7/17/2023 | APPLICANT |
| CofO in Progress | 2/21/2024 | EUGENE CASSIDY |
| CofO Issued | 2/22/2024 | ANSON MAGLASANG |
| Permit Finaled | 2/22/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2023 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2023 | ANA SORIANO |
| Sewer availability | Cleared | 5/4/2023 | ANA SORIANO |
| Low Impact Development (LID) | Cleared | 5/22/2023 | LUIS LUVANO |
Contact Information
| Architect | Soo,, Jonathan F J; Lic. No.: NA28196 | , |
| Contractor | Anchor Builders Inc; Lic. No.: 1029392-B | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/21/2023 | Corrections Issued | EUGENE CASSIDY |
| Sewer | 8/24/2023 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/30/2023 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Partial Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/19/2023 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 9/19/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/19/2023 | Approved | EUGENE CASSIDY |
| Insulation | 9/25/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/25/2023 | Approved | EUGENE CASSIDY |
| Wood Frame | 9/25/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 9/28/2023 | Approved | EUGENE CASSIDY |
| Service/Power Release | 10/13/2023 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 10/19/2023 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 10/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/21/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/21/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 11/21/2023 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 11/21/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 11/21/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 11/21/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/14/2024 | Approved | EUGENE CASSIDY |
| Final | 2/14/2024 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 2/14/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 2/14/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/14/2024 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 2/14/2024 | Approved | EUGENE CASSIDY |