18703 W SUNBURST ST 91324
Certificate Information: 18703 W SUNBURST ST 91324
- Application / Permit
- 23014-10000-01280
- Plan Check / Job No.
- B23LA06027
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground-floor addition (345 SF) to (E) 1-story SFD. All work per engineered plans
- Permit Issued
- Issued on 7/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2023 | MICHAEL LANZONE |
| Corrections Issued | 4/10/2023 | MICHAEL LANZONE |
| Building Plans Picked Up | 4/13/2023 | APPLICANT |
| Plan Check Approved | 5/31/2023 | MICHAEL LANZONE |
| Issued | 7/14/2023 | APPLICANT |
| CofO in Progress | 12/20/2023 | DAVID SCANTLIN |
| CofO Issued | 1/3/2024 | JOHN JANSON |
| Permit Finaled | 1/3/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2023 | SHAELYN ROWEN |
| Roof/Waste drainage to street | Cleared | 4/20/2023 | SHAELYN ROWEN |
| Sewer availability | Cleared | 4/20/2023 | SHAELYN ROWEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/19/2023 | Corrections Issued | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 7/21/2023 | Approved | DAVID SCANTLIN |
| Piling/Pier/Caisson | 7/21/2023 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 7/26/2023 | Corrections Issued | DAVID SCANTLIN |
| Underground Mechanical | 7/28/2023 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Approved | MORRIS JACKSON |
| Green Building Rough | 8/4/2023 | Not Ready for Inspection | MORRIS JACKSON |
| Wood Frame | 8/4/2023 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 8/22/2023 | Approved | JOHN KIDWELL |
| Shower Pan | 8/28/2023 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 9/22/2023 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 9/22/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 9/27/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 9/27/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 9/27/2023 | Partial Approval | JOHN KIDWELL |
| Insulation | 10/5/2023 | Corrections Issued | JOHN KIDWELL |
| Drywall Nailing | 10/13/2023 | Approved | JOHN KIDWELL |
| Insulation | 10/13/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 10/25/2023 | Partial Approval | JOHN KIDWELL |
| Final | 11/22/2023 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 11/22/2023 | Approved | DAVID SCANTLIN |
| Green Building Final | 11/22/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 11/22/2023 | Approved | DAVID SCANTLIN |
| Final | 12/20/2023 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 12/20/2023 | Approved | DAVID SCANTLIN |