1821 S MARINA DR 90732
Certificate Information: 1821 S MARINA DR 90732
- Application / Permit
- 23014-10000-01278
- Plan Check / Job No.
- B23LA06024
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) REAR PATIO COVER (342 SF), (N) 16'-0" X 10'-0" (160 SF) ADDITION, AND REMODEL TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE - ALL WORK PER DESIGN
- Permit Issued
- Issued on 12/29/2023
- Issuing Office
- Current Status
- CofO Issued on 11/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 4/10/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 8/18/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 11/8/2023 | KAMYAR EMAMI |
| Plan Check Approved | 12/17/2023 | ISIS ARGUETA |
| Issued | 12/29/2023 | APPLICANT |
| CofO in Progress | 11/14/2025 | JOSEPH MCGARRY |
| Permit Finaled | 11/17/2025 | ANSON MAGLASANG |
| CofO Issued | 11/17/2025 | ANSON MAGLASANG |
| Permit Finaled | 11/17/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/26/2023 | SERGIO VALENZUELA |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2023 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 11/3/2023 | ERIK BEASLEY |
| Hold | Cleared | 1/10/2024 | KRISTINE BUENAOBRA |
Contact Information
| Architect | Grist,, John Kenneth; Lic. No.: C4295 | 470 STANFORD DRIVE CLAREMONT, CA 91711 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/30/2024 | Conditional Approval | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 6/3/2024 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 6/3/2024 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 6/20/2024 | Partial Approval | ANSON MAGLASANG |
| Wood Frame | 6/20/2024 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Partial Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 9/9/2024 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Rough | 9/9/2024 | Approved | ANSON MAGLASANG |
| HVAC-Rough | 9/9/2024 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 9/9/2024 | Approved | ANSON MAGLASANG |
| Insulation | 9/13/2024 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 9/13/2024 | Partial Approval | ANSON MAGLASANG |
| Drywall Nailing | 9/30/2024 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/30/2024 | Approved | JOSEPH MCGARRY |
| Shower Pan | 9/30/2024 | Approved | JOSEPH MCGARRY |
| Final | 5/28/2025 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 5/28/2025 | Approved | JOHN KLARIN |
| Final | 11/13/2025 | OK to Issue CofO | JOSEPH MCGARRY |