8324 S ALVERSTONE AVE 90045

Certificate Information: 8324 S ALVERSTONE AVE 90045

Application / Permit
23014-10000-01264
Plan Check / Job No.
B23LA05995
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY ADDITION AT REAR OF EXISTING 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 9/14/2023
Issuing Office
Metro
Current Status
CofO Issued on 11/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 PRANITA SHAH
Corrections Issued 4/28/2023 PRANITA SHAH
Quality Review Completed 5/5/2023 KEN GILL
Building Plans Picked Up 5/9/2023 APPLICANT
Applicant returned to address corrections 8/23/2023 PRANITA SHAH
Plan Check Approved 9/14/2023 PRANITA SHAH
Issued 9/14/2023 APPLICANT
CofO in Progress 11/13/2024 MICHAEL ALLEN
Permit Finaled 11/19/2024 RICHARD STEINBACH
CofO Issued 11/19/2024 RICHARD STEINBACH
Permit Finaled 11/19/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/11/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/17/2023 DARIN LAM
Sewer availability Cleared 5/17/2023 DARIN LAM
Specific Plan Cleared 5/31/2023 JOSHUA JONES
Low Impact Development (LID) Cleared 8/3/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 8/7/2023 DARIN LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/21/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 11/27/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/14/2023 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 1/17/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 2/6/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 6/3/2024 Approved TEMISTOCLES CAAL
Special/Order Compliance 6/3/2024 Partial Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 6/17/2024 Approved TEMISTOCLES CAAL
Deputy Drilled-In Anchors 7/1/2024 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 7/2/2024 Approved TEMISTOCLES CAAL
Shower Pan 7/2/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 7/5/2024 Approved JESUS PINEDA
HVAC-Rough 7/5/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 7/9/2024 Partial Approval BOBBY KEY
Green Building Rough 7/9/2024 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 7/9/2024 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 7/11/2024 Corrections Issued JESUS RODRIGUEZ
Insulation 7/11/2024 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/26/2024 Approved TEMISTOCLES CAAL
Green Building Rough 7/26/2024 Approved TEMISTOCLES CAAL
Insulation 7/26/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 10/31/2024 SGSOV Not Ready MICHAEL ALLEN
ELECTRICAL-Final 11/1/2024 Approved MICHAEL ALLEN
HVAC-Final 11/1/2024 Approved MICHAEL ALLEN
PLUMBING-Final 11/1/2024 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 11/1/2024 Approved MICHAEL ALLEN
Final 11/12/2024 OK to Issue CofO MICHAEL ALLEN
Green Building Final 11/12/2024 Approved MICHAEL ALLEN
Service/Power Release 11/12/2024 Approved MICHAEL ALLEN