1272 W 18TH ST 90731
Certificate Information: 1272 W 18TH ST 90731
- Application / Permit
- 23014-10000-01246
- Plan Check / Job No.
- B23LA05867
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (eplan) ADDITION OF NEW BEDROOM WITH ROOF DECK ABOVE TO EXISTING 1-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 7/20/2023
- Issuing Office
- Current Status
- CofO Issued on 11/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2023 | YOUNG KIM |
| Corrections Issued | 4/11/2023 | YOUNG KIM |
| Quality Review Completed | 4/19/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/23/2023 | YOUNG KIM |
| Plan Check Approved | 7/19/2023 | YOUNG KIM |
| Issued | 7/20/2023 | APPLICANT |
| CofO in Progress | 11/15/2024 | ANSON MAGLASANG |
| Permit Finaled | 11/15/2024 | ANSON MAGLASANG |
| CofO Issued | 11/15/2024 | ANSON MAGLASANG |
| Permit Finaled | 11/15/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/2/2023 | SERGIO VALENZUELA |
| Roof/Waste drainage to street | Cleared | 6/8/2023 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2023 | ANA SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/26/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Partial Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 3/13/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 3/13/2024 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 3/13/2024 | Corrections Issued | JAMES CHAVEZ |
| Shower Pan | 3/13/2024 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 3/27/2024 | Corrections Issued | ANSON MAGLASANG |
| HVAC-Rough | 3/27/2024 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 3/27/2024 | Approved | ANSON MAGLASANG |
| Wood Frame | 4/9/2024 | Corrections Issued | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 4/12/2024 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Approved | JAMES CHAVEZ |
| Insulation | 4/18/2024 | Corrections Issued | JAMES CHAVEZ |
| Drywall Nailing | 4/25/2024 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 4/25/2024 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Final | 9/19/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 9/19/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 9/19/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 9/19/2024 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 9/19/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 10/11/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 10/11/2024 | Corrections Issued | EUGENE CASSIDY |
| Final | 11/15/2024 | OK to Issue CofO | ANSON MAGLASANG |
| Smoke Detectors | 11/15/2024 | Approved | ANSON MAGLASANG |