1812 S BURNSIDE AVE 90019

Certificate Information: 1812 S BURNSIDE AVE 90019

Application / Permit
23014-10000-01241
Plan Check / Job No.
B23LA05858
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERT DETACHED GARAGE TO ADU WITH NEW ADDITION PER ORDINANCE
Permit Issued
Issued on 8/18/2023
Issuing Office
Current Status
CofO Issued on 8/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2023 APPLICANT
Assigned to Plan Check Engineer 4/10/2023 DANIEL SANJUAN
Corrections Issued 4/11/2023 DANIEL SANJUAN
Applicant returned to address corrections 7/20/2023 VICTOR CHEN
Applicant returned to address corrections 8/3/2023 MINA HABILI
Plan Check Approved 8/4/2023 MINA HABILI
Issued 8/18/2023 APPLICANT
CofO in Progress 5/29/2024 ARTHUR NEGRETE
CofO Issued 8/6/2024 DEROLD HAUFF
Permit Finaled 8/6/2024 DEROLD HAUFF

Permit Application Clearance Information

Highway dedication Cleared 4/29/2023 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 5/5/2023 CHRISTOPHER ROCHA
Sewer availability Cleared 5/5/2023 CHRISTOPHER ROCHA
Low Impact Development (LID) Cleared 7/14/2023 MELINEH AGHAKHABIAN
Address approval Cleared 7/23/2023 AHMED AMARRAGY
Roof/Waste drainage to street Cleared 7/23/2023 AHMED AMARRAGY
Construction near power lines Cleared 8/1/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Xi,, Wang; Lic. No.: NA85148       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/17/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 10/26/2023 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 11/20/2023 Conditional Approval CHARLES BOGHOSKHAN
Footing/Foundation/Slab 11/28/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Corrections Issued BRENDAN MORELLI
Green Building Rough 1/2/2024 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Rough 1/22/2024 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 1/22/2024 Partial Approval STUART CHAPMAN
HVAC-Rough 1/22/2024 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 1/22/2024 Partial Approval STUART CHAPMAN
PLUMBING-Rough 1/22/2024 Approved STUART CHAPMAN
Insulation 1/29/2024 Corrections Issued RONNIE MINDANAO
PLUMBING-Rough 1/29/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 2/1/2024 Approved STUART CHAPMAN
Green Building Rough 2/1/2024 Approved STUART CHAPMAN
HVAC-Rough 2/1/2024 Approved STUART CHAPMAN
Insulation 2/1/2024 Approved STUART CHAPMAN
Drywall Nailing 2/9/2024 Approved ARTHUR NEGRETE
Final 3/18/2024 Corrections Issued STUART CHAPMAN
Green Building Final 3/18/2024 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 3/18/2024 Approved STUART CHAPMAN
Final 3/26/2024 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/26/2024 SGSOV Not Ready ENRIQUE MIRELES
Final 4/4/2024 Corrections Issued RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Approved RICHARD DOCKUS
ELECTRICAL-Final 4/8/2024 Approved ARTHUR NEGRETE
Final 5/15/2024 Corrections Issued ARTHUR NEGRETE
Final 5/28/2024 OK to Issue CofO ARTHUR NEGRETE
HVAC-Final 5/28/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 5/28/2024 Approved ARTHUR NEGRETE