5466 S 5TH AVE 90043
Certificate Information: 5466 S 5TH AVE 90043
- Application / Permit
- 23014-10000-01222
- Plan Check / Job No.
- B23LA05742
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE WITH ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 12/6/2023
- Issuing Office
- Current Status
- CofO Issued on 1/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 4/19/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/21/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 9/26/2023 | FARSHAD ALIMOHAMADI |
| Issued | 12/6/2023 | APPLICANT |
| CofO in Progress | 1/2/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 1/10/2025 | DEROLD HAUFF |
| Permit Finaled | 1/10/2025 | DEROLD HAUFF |
| CofO Issued | 1/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/29/2023 | NEIL TUANO |
| Roof/Waste drainage to street | Cleared | 6/30/2023 | NEIL TUANO |
| Construction near power lines | Cleared | 8/10/2023 | RIDWAN HARDY |
| Address approval | Cleared | 8/28/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2023 | NEIL TUANO |
| Hold | Cleared | 5/17/2024 | ALEXIS SCHULTZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/20/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/29/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 5/29/2024 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/6/2024 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/10/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/11/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 7/23/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 7/23/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 7/24/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 7/24/2024 | Approved | ANTHONY EGSON |
| Insulation | 7/31/2024 | Corrections Issued | ALEX COLIN |
| Interior/Exterior Lathing | 7/31/2024 | Corrections Issued | ALEX COLIN |
| BUILDING-Rough-Frame | 8/1/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 8/5/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/6/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 8/6/2024 | Approved | ANTHONY EGSON |
| Insulation | 8/6/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 8/12/2024 | No Access for Inspection | AMY COLIN |
| Interior/Exterior Lathing | 8/12/2024 | No Access for Inspection | AMY COLIN |
| Drywall Nailing | 8/14/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 8/14/2024 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 8/21/2024 | Corrections Issued | ANTHONY EGSON |
| Sewer | 8/21/2024 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 8/21/2024 | Corrections Issued | ANTHONY EGSON |
| Sewer | 9/10/2024 | Approved | ANTHONY EGSON |
| Underground Mechanical | 9/10/2024 | Approved | ANTHONY EGSON |
| Underground Mechanical | 9/23/2024 | Partial Approval | ANTHONY EGSON |
| Final | 12/4/2024 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 12/4/2024 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 12/4/2024 | Not Ready for Inspection | BARRY HACHE |
| Final | 12/16/2024 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 12/16/2024 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 12/16/2024 | Approved | BARRY HACHE |
| Final | 12/23/2024 | Corrections Issued | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Approved | LUIS CASTRO |
| ELECTRICAL-Final | 1/2/2025 | Approved | NICHOLAS LOPEZ |
| Final | 1/2/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| HVAC-Final | 1/2/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 1/2/2025 | Approved | NICHOLAS LOPEZ |