1543-1545 W 23RD ST 90007
Certificate Information: 1543-1545 W 23RD ST 90007
- Application / Permit
- 23014-10000-01220
- Plan Check / Job No.
- B23LA05735
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan ADD ATTACHED A.D.U. (409 SQ. FT.) TO EXISTING SINGLE FAMILY DWELLING Per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Current Status
- CofO Issued on 6/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2023 | DANIEL SANJUAN |
| Corrections Issued | 4/5/2023 | DANIEL SANJUAN |
| Applicant returned to address corrections | 6/14/2023 | ZAW HAN |
| Plan Check Approved | 7/18/2023 | ZAW HAN |
| Issued | 8/4/2023 | APPLICANT |
| CofO in Progress | 5/30/2024 | BRENDAN MORELLI |
| Permit Finaled | 6/6/2024 | DEROLD HAUFF |
| CofO Issued | 6/6/2024 | DEROLD HAUFF |
| Permit Finaled | 6/6/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 4/12/2023 | RYAN LY |
| Address approval | Cleared | 4/19/2023 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 4/19/2023 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2023 | ABEL CASILLAS |
| Sewer availability | Cleared | 4/21/2023 | ABEL CASILLAS |
| HPOZ | Cleared | 5/31/2023 | JONATHAN KAPLAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dominguez,, Refugio; Lic. No.: NA50820 | , |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/29/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 9/6/2023 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 9/25/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 9/25/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Underground Mechanical | 9/25/2023 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/27/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 9/27/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Underground Mechanical | 9/27/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 10/25/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Approved | RONNIE MINDANAO |
| Wood Frame | 10/27/2023 | Order to Comply Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/7/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 11/7/2023 | Approved | KATHRYN BUTTERWORTH |
| Rough-Elec/Plmb/HVAC | 11/7/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/14/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Rough-Elec/Plmb/HVAC | 11/14/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 11/16/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 11/16/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/20/2023 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 11/20/2023 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 11/20/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 11/20/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 11/20/2023 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 11/22/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 11/22/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Drywall Nailing | 11/29/2023 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 11/29/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 1/23/2024 | Corrections Issued | AMIR NAZARIAN |
| MERV13>=Final | 1/23/2024 | Partial Approval | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 1/23/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Smoke Detectors | 1/23/2024 | Approved | AMIR NAZARIAN |
| Final | 2/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 2/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/29/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Final | 2/29/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| PLUMBING-Final | 2/29/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 2/29/2024 | SGSOV Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 3/15/2024 | Approved | ARTHUR NEGRETE |
| Final | 3/15/2024 | Corrections Issued | ARTHUR NEGRETE |
| Final | 5/29/2024 | OK to Issue CofO | BRENDAN MORELLI |
| HVAC-Final | 5/29/2024 | Approved | BRENDAN MORELLI |
| Service/Power Release | 5/30/2024 | Approved | BRENDAN MORELLI |