10929 N HAYVENHURST AVE 91344

Certificate Information: 10929 N HAYVENHURST AVE 91344

Application / Permit
23014-10000-01219
Plan Check / Job No.
B23VN03218
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* GROUND FLOOR ADDITION TO (E) 1-STORY SFD
Permit Issued
Issued on 7/7/2023
Issuing Office
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2023 APPLICANT
Assigned to Plan Check Engineer 3/23/2023 VIVIAN LAO
Corrections Issued 3/29/2023 VIVIAN LAO
Quality Review Completed 3/31/2023 GARO TELMI
Applicant returned to address corrections 5/9/2023 VIVIAN LAO
Plan Check Approved 7/7/2023 VIVIAN LAO
Issued 7/7/2023 APPLICANT
CofO in Progress 6/22/2024 JAVIER RAMOS JR
Permit Finaled 7/24/2024 RUBEN SALAS
Permit Finaled 7/24/2024 RUBEN SALAS
CofO Issued 7/24/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/15/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 6/20/2023 FERNANDO GIL
Sewer availability Cleared 6/20/2023 FERNANDO GIL
Low Impact Development (LID) Cleared 6/26/2023 MELINEH AGHAKHABIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarian,, Varoojan; Lic. No.: NA94135       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/14/2023 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 7/14/2023 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 7/14/2023 Approved JAVIER RAMOS JR
Pre-Inspection 7/14/2023 Approved JAVIER RAMOS JR
Wood Frame 7/26/2023 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Partial Approval JAVIER RAMOS JR
Insulation 7/28/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 8/30/2023 Approved JACK KARGODORIAN
Wood Frame 8/30/2023 Corrections Issued JACK KARGODORIAN
Wood Frame 9/7/2023 Not Ready for Inspection JAVIER RAMOS JR
Deputy Wood Construction 9/13/2023 Conditional Approval ROBERT GOLD
Deputy Wood Construction 9/19/2023 Conditional Approval ROBERT GOLD
Wood Frame 9/25/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 10/2/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 10/2/2023 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 10/12/2023 Approved JAVIER RAMOS JR
Green Building Rough 10/12/2023 Approved JAVIER RAMOS JR
HVAC-Rough 10/12/2023 Approved JAVIER RAMOS JR
Insulation 10/12/2023 Approved JAVIER RAMOS JR
Drywall Nailing 10/19/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 10/19/2023 Approved JAVIER RAMOS JR
Shower Pan 10/19/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 4/2/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 4/2/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 4/2/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 4/2/2024 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 4/2/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/2/2024 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 4/2/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/2/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 5/2/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 5/2/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 5/2/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/7/2024 Approved JAVIER RAMOS JR
Final 6/21/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 6/21/2024 Approved JAVIER RAMOS JR