*EPLAN* ADD 11'-9" X 13'-9" TO REAR OF SINGLE FAMILY DWELLING
Permit Issued
Issued on 6/6/2023
Issuing Office
Current Status
CofO Issued on 9/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2023 APPLICANT
Assigned to Plan Check Engineer 4/4/2023 JOHNPAUL ISIP
Corrections Issued 4/5/2023 JOHNPAUL ISIP
Applicant returned to address corrections 4/20/2023 SELLA BENYAMIN
Applicant returned to address corrections 5/3/2023 SELLA BENYAMIN
Applicant returned to address corrections 5/8/2023 SELLA BENYAMIN
Applicant returned to address corrections 5/23/2023 MOHAMMAD ESMAILI
Plan Check Approved 6/6/2023 MOHAMMAD ESMAILI
Issued 6/6/2023 APPLICANT
CofO in Progress 9/7/2023 HERBERT GIRON
Permit Finaled 9/12/2023 DANIEL ORRANTE
CofO Issued 9/12/2023 DANIEL ORRANTE
Permit Finaled 9/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/13/2023 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 4/19/2023 ANTHONY MAINEZ
Specific Plan Cleared 5/10/2023 EDUARDO HERMOSO

Contact Information

Contractor Dreamers General Construction Inc; Lic. No.: 1025578-B       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/12/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 6/15/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Partial Approval BOBBY KEY
Insulation 6/23/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 6/23/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 7/6/2023 Corrections Issued HERBERT GIRON
Rough-Elec/Plmb/HVAC 7/17/2023 Partial Approval BOBBY KEY
Shower Pan 7/17/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Approved HERBERT GIRON
Insulation 7/19/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 7/25/2023 Corrections Issued BOBBY KEY
Green Building Rough 7/25/2023 Approved BOBBY KEY
Interior/Exterior Lathing 7/25/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 7/25/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 7/28/2023 Approved BOBBY KEY
Insulation 7/28/2023 Approved BOBBY KEY
Drywall Nailing 8/1/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 8/1/2023 Approved HERBERT GIRON
ELECTRICAL-Final 8/29/2023 Corrections Issued HERBERT GIRON
Final 8/29/2023 Corrections Issued HERBERT GIRON
HVAC-Final 8/29/2023 Approved HERBERT GIRON
PLUMBING-Final 8/29/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/29/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 8/29/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 9/7/2023 Approved HERBERT GIRON
Final 9/7/2023 OK to Issue CofO HERBERT GIRON
Green Building Final 9/7/2023 Approved HERBERT GIRON
PLUMBING-Final 9/7/2023 Approved HERBERT GIRON
Smoke Detectors 9/7/2023 Approved HERBERT GIRON