2208 E SHERIDAN ST 90033

Certificate Information: 2208 E SHERIDAN ST 90033

Application / Permit
23014-10000-01193
Plan Check / Job No.
B23LA05588
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) FRONT PATIO COVER AND (N) REAR ADDITION TO (E) SFD. CONVERT (E) FRONT PORCH TO (N) FOYER.
Permit Issued
Issued on 10/20/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2023 APPLICANT
Assigned to Plan Check Engineer 4/3/2023 JOSEPH RAFOLS
Corrections Issued 4/4/2023 JOSEPH RAFOLS
Building Plans Picked Up 4/6/2023 APPLICANT
Applicant returned to address corrections 5/22/2023 MINA HABILI
Plan Check Approved 7/12/2023 KHUONG TRUONG
Plan Check Approved 10/10/2023 FERNANDO FLORES
Issued 10/20/2023 APPLICANT
CofO in Progress 4/28/2025 ALIZAH MAYAGOITIA
Permit Finaled 5/3/2025 DEROLD HAUFF
CofO Issued 5/3/2025 DEROLD HAUFF
Permit Finaled 5/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Clean Up Green Up Cleared 4/18/2023 LOUIS ORTEGA
Low Impact Development (LID) Cleared 5/8/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 5/12/2023 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 5/22/2023 ABEL CASILLAS
GPI Written Notices Cleared 5/22/2023 JOSEPH RAFOLS
Grading Pre-Inspection Cleared 5/22/2023 JOSEPH RAFOLS
Sewer availability Cleared 5/22/2023 ABEL CASILLAS

Contact Information

Contractor Owner-Builder       ,
Engineer Phan,, Phillip Trung Tri; Lic. No.: C76425 641 S ALMIRANTE DR      WEST COVINA, CA 91791

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 1/26/2024 Approved OSVALDO PARAMO
Wood Frame 2/2/2024 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 4/8/2024 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Approved OSVALDO PARAMO
HVAC-Rough 4/8/2024 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 4/16/2024 Approved ALIZAH MAYAGOITIA
Green Building Rough 4/16/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/16/2024 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 4/16/2024 Approved ALIZAH MAYAGOITIA
Insulation 4/22/2024 Conditional Approval OSVALDO PARAMO
Drywall Nailing 5/8/2024 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/17/2024 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/23/2024 Approved OSVALDO PARAMO
Wood Frame 10/7/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/8/2024 Approved OSVALDO PARAMO
Final 11/27/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 11/27/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 11/27/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 11/27/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 11/27/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Sewer 12/27/2024 Approved JUSTIN HAWLEY
Final 1/17/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 1/17/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/17/2025 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 1/17/2025 Not Ready for Inspection LILIANA PORTILLO
Final 3/7/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 3/7/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 3/7/2025 Approved ALIZAH MAYAGOITIA
Final 4/24/2025 Conditional Approval ALIZAH MAYAGOITIA
Green Building Final 4/24/2025 Approved ALIZAH MAYAGOITIA
Final 4/28/2025 OK to Issue CofO ALIZAH MAYAGOITIA