2208 E SHERIDAN ST 90033
Certificate Information: 2208 E SHERIDAN ST 90033
- Application / Permit
- 23014-10000-01193
- Plan Check / Job No.
- B23LA05588
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) FRONT PATIO COVER AND (N) REAR ADDITION TO (E) SFD. CONVERT (E) FRONT PORCH TO (N) FOYER.
- Permit Issued
- Issued on 10/20/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2023 | JOSEPH RAFOLS |
| Corrections Issued | 4/4/2023 | JOSEPH RAFOLS |
| Building Plans Picked Up | 4/6/2023 | APPLICANT |
| Applicant returned to address corrections | 5/22/2023 | MINA HABILI |
| Plan Check Approved | 7/12/2023 | KHUONG TRUONG |
| Plan Check Approved | 10/10/2023 | FERNANDO FLORES |
| Issued | 10/20/2023 | APPLICANT |
| CofO in Progress | 4/28/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
| CofO Issued | 5/3/2025 | DEROLD HAUFF |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 4/18/2023 | LOUIS ORTEGA |
| Low Impact Development (LID) | Cleared | 5/8/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 5/12/2023 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2023 | ABEL CASILLAS |
| GPI Written Notices | Cleared | 5/22/2023 | JOSEPH RAFOLS |
| Grading Pre-Inspection | Cleared | 5/22/2023 | JOSEPH RAFOLS |
| Sewer availability | Cleared | 5/22/2023 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phan,, Phillip Trung Tri; Lic. No.: C76425 | 641 S ALMIRANTE DR WEST COVINA, CA 91791 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2024 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/26/2024 | Approved | OSVALDO PARAMO |
| Wood Frame | 2/2/2024 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 4/8/2024 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2024 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 4/8/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/16/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/16/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/16/2024 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 4/16/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 4/22/2024 | Conditional Approval | OSVALDO PARAMO |
| Drywall Nailing | 5/8/2024 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 9/17/2024 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 9/23/2024 | Approved | OSVALDO PARAMO |
| Wood Frame | 10/7/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/8/2024 | Approved | OSVALDO PARAMO |
| Final | 11/27/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 11/27/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Final | 11/27/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 11/27/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 11/27/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Sewer | 12/27/2024 | Approved | JUSTIN HAWLEY |
| Final | 1/17/2025 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 1/17/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 1/17/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 3/7/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 3/7/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/24/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 4/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/28/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |