810 S AVENUE 60 90042
Certificate Information: 810 S AVENUE 60 90042
- Application / Permit
- 23014-10000-01149
- Plan Check / Job No.
- B23LA05360
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan. One story addtion to an existing one story single family dwelling with a basement garge.
- Permit Issued
- Issued on 3/20/2024
- Issuing Office
- Current Status
- Issued on 3/20/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2023 | KESETE HAREGOT |
| Corrections Issued | 4/26/2023 | KESETE HAREGOT |
| Quality Review Completed | 5/2/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 10/3/2023 | KESETE HAREGOT |
| No Progress | 3/13/2024 | KESETE HAREGOT |
| Applicant returned to address corrections | 3/13/2024 | KESETE HAREGOT |
| Plan Check Approved | 3/15/2024 | KESETE HAREGOT |
| Issued | 3/20/2024 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 6/9/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 7/17/2023 | LUIS LUVANO |
| "D" conditions | Cleared | 7/31/2023 | SPENCER WEJROWSKI |
| "Q" conditions | Cleared | 7/31/2023 | SPENCER WEJROWSKI |
| Roof/Waste drainage to street | Cleared | 8/24/2023 | JOSEPH RHYU |
| BHO/Hillside ordinance | Cleared | 10/5/2023 | JOSEPH RHYU |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2023 | JOSEPH RHYU |
| GPI Written Notices | Cleared | 11/8/2023 | KESETE HAREGOT |
| Grading Pre-Inspection | Cleared | 11/8/2023 | KESETE HAREGOT |
| BHO/Hillside ordinance | Cleared | 2/23/2024 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 3/4/2024 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 3/4/2024 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 3/4/2024 | WALLIE JONG |
| ZA Case | Cleared | 3/12/2024 | MAYELA VILLA |
| Green Code | Cleared | 3/13/2024 | KESETE HAREGOT |
Contact Information
| Architect | Bo, Kyle Sundius; Lic. No.: C38566 | 1814 BROOKS AVE LOS ANGELES, CA 90012 |
| Contractor | M S Elite General Construction Inc; Lic. No.: 660454-B | , |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/22/2024 | Corrections Issued | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/1/2024 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/22/2024 | Partial Approval | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 5/23/2024 | Conditional Approval | LILIANA PORTILLO |
| Deputy Other (see comments) | 5/23/2024 | Conditional Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/31/2024 | Corrections Issued | LILIANA PORTILLO |
| Piling/Pier/Caisson | 5/31/2024 | Corrections Issued | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 6/26/2024 | Conditional Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/5/2024 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 8/7/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/9/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Corrections Issued | BRENDAN MORELLI |
| Underground Mechanical | 9/18/2024 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Partial Approval | ROY SPAULDING |
| Underground Mechanical | 9/25/2024 | Partial Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Partial Approval | LILIANA PORTILLO |
| Gas Test | 2/13/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 2/13/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 2/27/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/7/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 3/7/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 3/7/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/17/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 3/17/2025 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/17/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/18/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/18/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 3/18/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/18/2025 | Partial Approval | LILIANA PORTILLO |
| Insulation | 3/25/2025 | Partial Approval | REGINA MENDEZ |
| Interior/Exterior Lathing | 4/3/2025 | Approved | LILIANA PORTILLO |
| Shower Pan | 4/3/2025 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 4/16/2025 | Approved | LILIANA PORTILLO |
| Gas Test | 4/16/2025 | Approved | LILIANA PORTILLO |
| Final | 10/15/2025 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/15/2025 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 10/15/2025 | Approved | LILIANA PORTILLO |
| Final | 1/20/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 1/20/2026 | SGSOV Approved | LILIANA PORTILLO |