5612 W SPOKANE ST 90016
Certificate Information: 5612 W SPOKANE ST 90016
- Application / Permit
- 23014-10000-01132
- Plan Check / Job No.
- B23LA05298
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERT (E) DETACHED GARAGE TO ADU PER ORDINANCE AND LAMC 12.22 A33(c)&(d).
- Permit Issued
- Issued on 8/17/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2023 | ZAW HAN |
| Corrections Issued | 4/3/2023 | ZAW HAN |
| Building Plans Picked Up | 4/6/2023 | APPLICANT |
| Plan Check Approved | 6/2/2023 | KHUONG TRUONG |
| Issued | 8/17/2023 | APPLICANT |
| CofO in Progress | 7/19/2024 | ARTHUR NEGRETE |
| Permit Finaled | 3/30/2025 | DEROLD HAUFF |
| CofO Issued | 3/30/2025 | DEROLD HAUFF |
| Permit Finaled | 3/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/26/2023 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 4/26/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 6/2/2023 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Quantum Construction & Design; Lic. No.: 1061867-B | 3646 W SLAUSON AVE LOS ANGELES, CA 90043 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/8/2023 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 9/13/2023 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 10/27/2023 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 10/27/2023 | Partial Approval | RONNIE MINDANAO |
| PLUMBING-Rough | 10/27/2023 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 11/8/2023 | Approved | JOSE AVILA |
| Underground Mechanical | 11/8/2023 | Partial Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 11/20/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/22/2023 | Approved | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 11/22/2023 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2023 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 11/22/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Underground Mechanical | 11/22/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 11/29/2023 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/1/2023 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 12/4/2023 | Corrections Issued | RONNIE MINDANAO |
| Insulation | 12/8/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 12/8/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 12/19/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Insulation | 12/19/2023 | Conditional Approval | RONNIE MINDANAO |
| Insulation | 12/20/2023 | No Access for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 12/26/2023 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 12/29/2023 | Not Ready for Inspection | JOSH MEISTER |
| Footing/Foundation/Slab | 1/3/2024 | Partial Approval | RONNIE MINDANAO |
| Drywall Nailing | 1/10/2024 | Approved | STUART CHAPMAN |
| Green Building Rough | 1/10/2024 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 1/10/2024 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/28/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 6/28/2024 | Corrections Issued | ARTHUR NEGRETE |
| PLUMBING-Rough | 6/28/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 7/2/2024 | Approved | SCOTT FINNILA |
| Final | 7/2/2024 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 7/2/2024 | Approved | SCOTT FINNILA |
| HVAC-Final | 7/2/2024 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 7/2/2024 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 7/16/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 7/16/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 7/16/2024 | Approved | ARTHUR NEGRETE |
| Final | 7/18/2024 | OK to Issue CofO | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 7/18/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 7/18/2024 | Approved | ARTHUR NEGRETE |