2702 S HARCOURT AVE 90016
Certificate Information: 2702 S HARCOURT AVE 90016
- Application / Permit
- 23014-10000-01123
- Plan Check / Job No.
- B23LA05253
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREGULAR ADDITION TO SFD TO ADD NEW BEDROOM, NEW BATH, AND EXTEND EXISTING BEDROOM.
- Permit Issued
- Issued on 3/12/2025
- Issuing Office
- Current Status
- CofO Issued on 3/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2023 | ISIS ARGUETA |
| Corrections Issued | 3/29/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 1/21/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 2/20/2025 | ALEC MOUSAKHANIAN |
| Issued | 3/12/2025 | APPLICANT |
| CofO in Progress | 3/5/2026 | JUSTIN HAWLEY |
| Permit Finaled | 3/7/2026 | DEROLD HAUFF |
| CofO Issued | 3/7/2026 | DEROLD HAUFF |
| Permit Finaled | 3/7/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/20/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2025 | JEANIE LAM |
| Sewer availability | Cleared | 2/14/2025 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/9/2025 | Partial Approval | WILLIAM SIERRA |
| Deputy Drilled-In Anchors | 5/21/2025 | Conditional Approval | FREDDIE RIVERA |
| Wood Frame | 5/21/2025 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Partial Approval | JUSTIN HAWLEY |
| Underground Mechanical | 6/5/2025 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 6/23/2025 | Partial Approval | JUSTIN HAWLEY |
| Wood Frame | 7/16/2025 | No Access for Inspection | JUSTIN HAWLEY |
| Wood Frame | 7/18/2025 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/22/2025 | Partial Approval | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 9/22/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 9/22/2025 | Corrections Issued | ARTHUR NEGRETE |
| Wood Frame | 9/22/2025 | Partial Approval | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 10/8/2025 | Partial Approval | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 10/8/2025 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/16/2025 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 10/16/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 11/7/2025 | No Access for Inspection | MICHAEL LEWIS |
| Insulation | 11/13/2025 | Approved | ALEX COLIN |
| Shower Pan | 11/13/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 11/19/2025 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 11/19/2025 | Partial Inspection | WILLIAM SIERRA |
| Interior/Exterior Lathing | 12/10/2025 | Approved | JUSTIN HAWLEY |
| Final | 2/19/2026 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 2/19/2026 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 2/19/2026 | SGSOV Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 3/5/2026 | Approved | JUSTIN HAWLEY |
| Final | 3/5/2026 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 3/5/2026 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 3/5/2026 | Approved | JUSTIN HAWLEY |
| Smoke Detectors | 3/5/2026 | Approved | JUSTIN HAWLEY |