12360 W CANTURA ST 91604

Certificate Information: 12360 W CANTURA ST 91604

Application / Permit
23014-10000-01122
Plan Check / Job No.
B23LA05250
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan (E) GARAGE CONVERT TO ADU WITH ADDITION PER LAMC 12.22 A.33 (c)(d).
Permit Issued
Issued on 8/30/2023
Issuing Office
Current Status
CofO Issued on 5/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2023 APPLICANT
Assigned to Plan Check Engineer 3/31/2023 KHUONG TRUONG
Corrections Issued 4/2/2023 KHUONG TRUONG
Applicant returned to address corrections 5/4/2023 MICHAEL LOPEZ
Plan Check Approved 8/9/2023 MICHAEL LOPEZ
No Progress 8/23/2023 MICHAEL LOPEZ
Plan Check Approved 8/23/2023 MICHAEL LOPEZ
No Progress 8/23/2023 MICHAEL LOPEZ
Plan Check Approved 8/23/2023 MICHAEL LOPEZ
No Progress 8/29/2023 MICHAEL LOPEZ
Plan Check Approved 8/29/2023 MICHAEL LOPEZ
Issued 8/30/2023 APPLICANT
CofO in Progress 5/13/2024 MICHEL ABAJAN
Permit Finaled 5/31/2024 RUBEN SALAS
CofO Issued 5/31/2024 RUBEN SALAS
Permit Finaled 5/31/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/25/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 4/25/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/2/2023 MEGAN GODINEZ
Grading Pre-Inspection Cleared 5/2/2023 SERGIO VALENZUELA
HPOZ Cleared 5/2/2023 LAMBERT GIESSINGER
Hist. Property Cntrct Mgr Appr Cleared 5/2/2023 LAMBERT GIESSINGER
Historic monument Cleared 5/2/2023 LAMBERT GIESSINGER
Sewer availability Cleared 5/2/2023 MEGAN GODINEZ
Construction near power lines Cleared 7/22/2023 TINA MIRANDA

Contact Information

Contractor Silva Israel Electric & Plumbing; Lic. No.: 524577-B       ,
Engineer Nazari,, Arthur; Lic. No.: NA53497       ,

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/19/2023 Approved CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 9/26/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/26/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 9/28/2023 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Approved JOHN COLEMAN
BUILDING-Rough-Frame 10/23/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 10/23/2023 Approved CHRISTOPHE COCHRAN
Green Building Rough 10/23/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/6/2023 Partial Approval CHRISTOPHE COCHRAN
Rough-Elec/Plmb/HVAC 11/15/2023 Not Ready for Inspection JOHN COLEMAN
BUILDING-Rough-Frame 11/22/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/22/2023 Partial Approval CHRISTOPHE COCHRAN
Rough-Elec/Plmb/HVAC 11/22/2023 Approved CHRISTOPHE COCHRAN
Shower Pan 11/22/2023 Approved CHRISTOPHE COCHRAN
Insulation 11/29/2023 Approved CHRISTOPHE COCHRAN
Drywall Nailing 12/4/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/4/2023 Approved CHRISTOPHE COCHRAN
Final 2/12/2024 Partial Inspection MISAEL ESPARZA
Green Building Final 2/12/2024 Partial Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 2/12/2024 Partial Inspection MISAEL ESPARZA
Final 2/26/2024 No Access for Inspection CHRISTOPHE COCHRAN
Green Building Final 2/26/2024 No Access for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Not Ready CHRISTOPHE COCHRAN
Smoke Detectors 2/26/2024 No Access for Inspection CHRISTOPHE COCHRAN
Final 2/28/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 2/28/2024 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 2/28/2024 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 2/28/2024 Approved CHRISTOPHE COCHRAN
Final 3/7/2024 Corrections Issued KIRK SANDERS
Final 3/20/2024 Corrections Issued CHRISTOPHE COCHRAN
Final 4/8/2024 Corrections Issued CHRISTOPHE COCHRAN
Final 5/13/2024 OK to Issue CofO MICHEL ABAJAN