12609 W WELBY WAY 91606

Certificate Information: 12609 W WELBY WAY 91606

Application / Permit
23014-10000-01102
Plan Check / Job No.
B23LA05164
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
173 SF ADDITION T REAR AND REMODEL TO EXISTING ONE STORY SINGLE FAMILY DEWLLING PER ENGINEER DETAILS
Permit Issued
Issued on 7/19/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2023 APPLICANT
Assigned to Plan Check Engineer 3/28/2023 AUNG SOE
Corrections Issued 3/30/2023 AUNG SOE
Building Plans Picked Up 3/31/2023 APPLICANT
Plan Check Approved 7/14/2023 JOSEPH RAFOLS
Issued 7/19/2023 APPLICANT
CofO in Progress 1/6/2025 DAVID MATSON
Permit Finaled 1/9/2025 RUBEN SALAS
CofO Issued 1/9/2025 RUBEN SALAS
Permit Finaled 1/9/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/16/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 5/16/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/19/2023 DAGOVERTO GUERRERO

Contact Information

Architect Hurtado,, Jesus; Lic. No.: C29969 1310 S MCDONNELL AVENUE      LOS ANGELES, CA 90022
Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/20/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/22/2023 Approved KIRK SANDERS
Wood Frame 10/6/2023 Partial Approval KIRK SANDERS
Wood Frame 10/12/2023 Corrections Issued CHRISTOPHER ROJAS
Pre-Inspection 10/17/2023 Approved KIRK SANDERS
Wood Frame 10/17/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 2/23/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 2/23/2024 Corrections Issued JOSE AVILA
HVAC-Rough 3/4/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 3/8/2024 Approved JOSE AVILA
Green Building Rough 3/8/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 3/13/2024 Approved JOSE AVILA
HVAC-Rough 3/13/2024 Approved JOSE AVILA
Interior/Exterior Lathing 3/13/2024 Approved JOSE AVILA
Insulation 3/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 4/3/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/23/2024 Corrections Issued SALVADOR MARTINEZ
Shower Pan 5/23/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 5/28/2024 Approved JOSE AVILA
Shower Pan 5/28/2024 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 9/18/2024 Partial Approval OGANES TARAKHCHYAN
Final 12/23/2024 OK to Issue CofO DAVID MATSON
Green Building Final 12/23/2024 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Approved DAVID MATSON
Smoke Detectors 12/23/2024 Approved DAVID MATSON