3008 1/2 N TYBURN ST 90039
Certificate Information: 3008 1/2 N TYBURN ST 90039
- Application / Permit
- 23014-10000-01099
- Plan Check / Job No.
- B23LA05158
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* GROUND FLOOR ADDITION AND 2ND STORY ADDITION TO (E) 1-STORY DETACHED ADU PER LAMC 12.22.A.33(c)-(d).
- Permit Issued
- Issued on 6/21/2023
- Issuing Office
- Current Status
- CofO Issued on 3/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | VIVIAN LAO |
| Corrections Issued | 4/20/2023 | VIVIAN LAO |
| Quality Review Completed | 4/20/2023 | GARO TELMI |
| Plan Check Approved | 6/14/2023 | VIVIAN LAO |
| Issued | 6/21/2023 | APPLICANT |
| CofO in Progress | 2/25/2025 | THOMAS LOGRASSO |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
| CofO Issued | 3/2/2025 | DEROLD HAUFF |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 5/1/2023 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 5/16/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 5/16/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2023 | HUGO LOPEZ |
| Construction within easement | Cleared | 6/5/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/29/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/5/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/5/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/13/2023 | Not Ready for Inspection | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | Corrections Issued | ROY SPAULDING |
| PLUMBING-Rough | 10/13/2023 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 10/17/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 10/17/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/17/2023 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/11/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/11/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 12/11/2023 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/21/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 12/21/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 12/21/2023 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 12/21/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 1/19/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Gas Test | 1/19/2024 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/26/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 7/30/2024 | Approved | THOMAS LOGRASSO |
| Final | 7/30/2024 | Partial Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 7/30/2024 | SGSOV Not Ready | THOMAS LOGRASSO |
| Final | 2/12/2025 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 2/12/2025 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 2/12/2025 | Approved | THOMAS LOGRASSO |
| Final | 2/24/2025 | OK to Issue CofO | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 2/24/2025 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 2/24/2025 | Not Required | THOMAS LOGRASSO |