16940 W HARTLAND ST 91406

Certificate Information: 16940 W HARTLAND ST 91406

Application / Permit
23014-10000-01066
Plan Check / Job No.
B23VN03263
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION AND ADDITION TO (E) GARAGE TO (N) ADU PER GCS 65852.2(e)(1)(B)
Permit Issued
Issued on 7/25/2023
Issuing Office
Current Status
CofO in Progress on 1/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/16/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 NGHI SU
Corrections Issued 3/18/2023 NGHI SU
Quality Review Completed 3/24/2023 GARO TELMI
Applicant returned to address corrections 6/8/2023 NGHI SU
Plan Check Approved 6/29/2023 NGHI SU
Issued 7/25/2023 APPLICANT
CofO in Progress 8/20/2024 MORRIS JACKSON
No Progress 1/10/2025 SEAN WIRCH
CofO in Progress 1/10/2025 SEAN WIRCH

Permit Application Clearance Information

Address approval Cleared 4/14/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 4/17/2023 NIKKI ZULUETA
Sewer availability Cleared 4/17/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 6/21/2023 NIKKI ZULUETA

Contact Information

Contractor Owner-Builder       ,
Engineer Lombera,, Raymundo Alcaraz; Lic. No.: L7740 135 S JACKSON STREET #202      GLENDALE, CA 91205
Engineer Samvelyan,, Taron; Lic. No.: C93740 1800 N VERDUGO RD APT 204      GLENDALE, CA 91208
Engineer Samvelyan,, Taron; Lic. No.: NA93740       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/8/2023 Approved JON MCHUGH
Excavation/Setback/Form/Re-Bar 12/8/2023 Partial Approval JON MCHUGH
Pre-Inspection 12/8/2023 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Partial Approval JON MCHUGH
Underground Mechanical 1/12/2024 Approved JON MCHUGH
Wood Frame 1/12/2024 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 3/28/2024 Approved ALEXANDER HANDY
HVAC-Rough 3/28/2024 Approved ALEXANDER HANDY
Shower Pan 3/28/2024 Approved ALEXANDER HANDY
Wood Frame 3/28/2024 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 4/8/2024 Partial Approval JON MCHUGH
Insulation 4/8/2024 Approved JON MCHUGH
Interior/Exterior Lathing 4/8/2024 Partial Approval JON MCHUGH
BUILDING-Rough-Frame 4/17/2024 Corrections Issued ARUTYUN MADATYAN
Drywall Nailing 4/17/2024 Partial Approval ARUTYUN MADATYAN
Green Building Rough 4/17/2024 Not Ready for Inspection ARUTYUN MADATYAN
Interior/Exterior Lathing 4/17/2024 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 8/9/2024 Approved MORRIS JACKSON
Drywall Nailing 8/9/2024 Approved MORRIS JACKSON
Final 8/9/2024 OK to Issue CofO MORRIS JACKSON
Footing/Foundation/Slab 8/9/2024 Approved MORRIS JACKSON
Green Building Final 8/9/2024 Approved MORRIS JACKSON
Green Building Rough 8/9/2024 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 8/9/2024 SGSOV Approved MORRIS JACKSON
Smoke Detectors 8/9/2024 Approved MORRIS JACKSON
Service/Power Release 8/14/2024 Approved MORRIS JACKSON