5801 N HESPERIA AVE 91316
Certificate Information: 5801 N HESPERIA AVE 91316
- Application / Permit
- 23014-10000-01044
- Plan Check / Job No.
- B23LA04911
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and Remodel to (E) SFD eplan: SFD (1,213sq.ft.) remodeling with additions at front and rear: 1. rear addition 696 sq.ft. new master bedroom & bathroom, kitchen, family room. 2. front addition 119.30 sq.ft. addition to (e) den, convert to bedroom w/ bathroom. 3. new covered porch 61.45 sqft. New roof allover.
- Permit Issued
- Issued on 7/14/2023
- Issuing Office
- Current Status
- CofO Issued on 1/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2023 | HERNAN ARREOLA |
| Corrections Issued | 4/16/2023 | HERNAN ARREOLA |
| Quality Review Completed | 4/19/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 7/10/2023 | HERNAN ARREOLA |
| Issued | 7/14/2023 | APPLICANT |
| CofO in Progress | 10/4/2024 | JON MCHUGH |
| No Progress | 1/10/2025 | SEAN WIRCH |
| CofO in Progress | 1/10/2025 | SEAN WIRCH |
| Permit Finaled | 1/23/2025 | JOHN JANSON |
| CofO Issued | 1/23/2025 | JOHN JANSON |
| Permit Finaled | 1/23/2025 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 6/6/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 6/9/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/12/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/12/2023 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 6/12/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Levin,, Vladimir; Lic. No.: C35001 | 11606 CHENAULT STR, UNIT 301 LOS ANGELES, CA 90049 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/26/2023 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 7/26/2023 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 7/26/2023 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 8/3/2023 | Corrections Issued | JON MCHUGH |
| Deputy Reinf. Concrete | 8/4/2023 | Conditional Approval | JON MCHUGH |
| PLUMBING-Rough | 8/16/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 8/18/2023 | Corrections Issued | JON MCHUGH |
| Deputy Drilled-In Anchors | 8/18/2023 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 8/18/2023 | Conditional Approval | JON MCHUGH |
| Insulation | 8/23/2023 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2023 | Partial Approval | JON MCHUGH |
| Deputy Drilled-In Anchors | 10/6/2023 | Conditional Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 10/10/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 10/10/2023 | Not Ready for Inspection | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 10/10/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | Partial Approval | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 10/27/2023 | Corrections Issued | JON MCHUGH |
| Wood Frame | 10/27/2023 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 11/3/2023 | Approved | JON MCHUGH |
| Green Building Rough | 11/3/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 11/3/2023 | Partial Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 11/3/2023 | Approved | JON MCHUGH |
| Insulation | 11/8/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 11/21/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 11/21/2023 | Approved | JON MCHUGH |
| Shower Pan | 11/21/2023 | Approved | JON MCHUGH |
| Special/Order Compliance | 3/7/2024 | Corrections Issued | SEAN WIRCH |
| Final | 9/12/2024 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 9/12/2024 | Approved | JON MCHUGH |
| Green Building Final | 9/12/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 9/12/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 10/3/2024 | Approved | JON MCHUGH |
| Final | 10/3/2024 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 10/3/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 10/3/2024 | Approved | JON MCHUGH |
| Smoke Detectors | 10/3/2024 | Approved | JON MCHUGH |