5706 N BURNET AVE 91411
Certificate Information: 5706 N BURNET AVE 91411
- Application / Permit
- 23014-10000-01012
- Plan Check / Job No.
- B23LA04723
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. CONVERT (E) DETACHED GARAGE AND (N) ADDITION TO (N) ADU
- Permit Issued
- Issued on 1/25/2024
- Issuing Office
- Current Status
- CofO Issued on 9/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2023 | RAHEL BEYENE |
| Corrections Issued | 3/30/2023 | RAHEL BEYENE |
| Applicant returned to address corrections | 8/2/2023 | AUNG SOE |
| Applicant returned to address corrections | 1/11/2024 | FERNANDO FLORES |
| Plan Check Approved | 1/19/2024 | FERNANDO FLORES |
| Issued | 1/25/2024 | APPLICANT |
| CofO in Progress | 8/29/2024 | RYAN SALAZAR |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
| CofO Issued | 9/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 6/12/2023 | BRENNEN OBETO |
| Address approval | Cleared | 6/13/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 6/15/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 7/6/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 7/7/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 1/17/2024 | OSCAR CASTRO |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/27/2024 | Partial Approval | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 3/1/2024 | Conditional Approval | JOHN COLEMAN |
| Footing/Foundation/Slab | 3/1/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 4/15/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 4/15/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 4/15/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 4/15/2024 | Approved | RYAN SALAZAR |
| Insulation | 4/19/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/19/2024 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 5/2/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 6/24/2024 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Final | 7/2/2024 | Approved | RYAN SALAZAR |
| Final | 8/5/2024 | Corrections Issued | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 8/5/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 8/5/2024 | Approved | RYAN SALAZAR |
| Final | 8/27/2024 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 8/27/2024 | Approved | RYAN SALAZAR |