2507 S EASTERN CT 90291

Certificate Information: 2507 S EASTERN CT 90291

Application / Permit
23014-10000-01007
Plan Check / Job No.
B23LA04690
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2ND FLOOR BALCONY ENCLOSURES AND INTERIOR REMODEL OF ADJACENT AREAS PER DIR 2020-2172-CDP.
Permit Issued
Issued on 7/6/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2023 APPLICANT
Assigned to Plan Check Engineer 3/23/2023 LAWRENCE QUIRANTE
Corrections Issued 3/30/2023 LAWRENCE QUIRANTE
Building Plans Picked Up 4/6/2023 APPLICANT
Plan Check Approved 7/6/2023 CRISTINA SALAZAR
Issued 7/6/2023 APPLICANT
CofO in Progress 1/17/2025 HERBERT GIRON
CofO Issued 2/12/2025 RICHARD STEINBACH
Permit Finaled 2/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 4/19/2023 ALESSANDRO MERCURI
Roof/Waste drainage to street Cleared 5/1/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/3/2023 DARIN LAM
Sewer availability Cleared 5/3/2023 DARIN LAM
City Hist. Cultural Monument Cleared 5/4/2023 LAMBERT GIESSINGER
Historic monument Cleared 5/4/2023 LAMBERT GIESSINGER
Coastal Zone Cleared 5/15/2023 LOUIS ORTEGA
Miscellaneous Cleared 5/15/2023 LOUIS ORTEGA
Specific Plan Cleared 5/15/2023 LOUIS ORTEGA

Contact Information

Contractor Owner-Builder       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/1/2023 Partial Inspection HERBERT GIRON
Deputy Drilled-In Anchors 1/26/2024 Conditional Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 1/31/2024 Approved HERBERT GIRON
Footing/Foundation/Slab 1/31/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 4/29/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 5/7/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 5/7/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 5/7/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 5/21/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Approved HERBERT GIRON
Green Building Rough 5/21/2024 Approved HERBERT GIRON
HVAC-Rough 5/21/2024 Conditional Approval HERBERT GIRON
Insulation 5/21/2024 Approved HERBERT GIRON
Drywall Nailing 5/30/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 5/30/2024 Approved HERBERT GIRON
ELECTRICAL-Final 8/15/2024 Corrections Issued HERBERT GIRON
Final 8/15/2024 Corrections Issued HERBERT GIRON
Green Building Final 8/15/2024 Approved HERBERT GIRON
HVAC-Final 8/15/2024 Approved HERBERT GIRON
PLUMBING-Final 8/15/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/15/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 8/15/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 8/23/2024 Approved HERBERT GIRON
Final 8/23/2024 Corrections Issued HERBERT GIRON
Smoke Detectors 8/23/2024 Approved HERBERT GIRON
Final 1/17/2025 OK to Issue CofO HERBERT GIRON