1053 W 77TH ST 90044
Certificate Information: 1053 W 77TH ST 90044
- Application / Permit
- 23014-10000-01003
- Plan Check / Job No.
- B23LA04651
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE AND EXPAND TO CREATE A.D.U. PER ORDINANCE. CONST. PER W.F.P.P.
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Current Status
- CofO Issued on 11/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 3/24/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 3/24/2023 | APPLICANT |
| Plan Check Approved | 6/2/2023 | SAMUEL GONZALEZ |
| Issued | 6/2/2023 | APPLICANT |
| CofO in Progress | 11/15/2023 | MICHAEL LEWIS |
| Permit Finaled | 11/17/2023 | DEROLD HAUFF |
| CofO Issued | 11/17/2023 | DEROLD HAUFF |
| Permit Finaled | 11/17/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/3/2023 | WALTER RAMIREZ |
| Address approval | Cleared | 5/10/2023 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/10/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2023 | ADRIAN SANCHEZ |
| Low Impact Development (LID) | Cleared | 6/2/2023 | JORGE MEJIA LEMUS |
| Sewer availability | Cleared | 6/2/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Daniel Pascuale; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/20/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 7/20/2023 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 7/31/2023 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/31/2023 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 8/24/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 8/24/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/6/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 9/6/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 9/6/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/7/2023 | Approved | MICHAEL LEWIS |
| Insulation | 9/14/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 9/14/2023 | Approved | MICHAEL LEWIS |
| Insulation | 9/15/2023 | Partial Inspection | MICHAEL LEWIS |
| Drywall Nailing | 9/18/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 9/18/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 11/9/2023 | Approved | MICHAEL LEWIS |
| Final | 11/9/2023 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 11/9/2023 | Approved | MICHAEL LEWIS |
| Gas Test | 11/9/2023 | Approved | MICHAEL LEWIS |
| HVAC-Final | 11/9/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 11/9/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 11/9/2023 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 11/9/2023 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 11/9/2023 | Approved | MICHAEL LEWIS |
| Final | 11/14/2023 | OK to Issue CofO | MICHAEL LEWIS |