1612 N MARINE AVE 90744

Certificate Information: 1612 N MARINE AVE 90744

Application / Permit
23014-10000-00992
Plan Check / Job No.
B23LA04603
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert detached 2-car garage to ADU per state law and addition of a 1-car garage.
Permit Issued
Issued on 4/26/2023
Issuing Office
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2023 APPLICANT
Assigned to Plan Check Engineer 3/22/2023 JOSEPH RAFOLS
Corrections Issued 3/23/2023 JOSEPH RAFOLS
Applicant returned to address corrections 4/13/2023 MINA HABILI
Plan Check Approved 4/22/2023 MINA HABILI
Issued 4/26/2023 APPLICANT
CofO in Progress 4/14/2024 EUGENE CASSIDY
Permit Finaled 4/15/2024 ANSON MAGLASANG
CofO Issued 4/15/2024 ANSON MAGLASANG

Permit Application Clearance Information

Clean Up Green Up Cleared 3/24/2023 KENTON TRINH
Address approval Cleared 3/28/2023 ANA SORIANO
Roof/Waste drainage to street Cleared 3/28/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 4/11/2023 ANA SORIANO
Sewer availability Cleared 4/11/2023 ANA SORIANO

Contact Information

Architect Haro,, Ruben; Lic. No.: NA38528       ,
Contractor Owner-Builder       ,
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/9/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 8/28/2023 Partial Approval EUGENE CASSIDY
Sewer 8/28/2023 Approved EUGENE CASSIDY
Footing/Foundation/Slab 10/6/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 10/6/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 10/6/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 10/12/2023 Approved EUGENE CASSIDY
METHANE-Barrier 10/12/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 10/12/2023 Approved EUGENE CASSIDY
Wood Frame 11/9/2023 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 11/21/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/22/2023 Approved EUGENE CASSIDY
Green Building Rough 11/22/2023 Approved EUGENE CASSIDY
HVAC-Rough 11/22/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/22/2023 Partial Approval EUGENE CASSIDY
METHANE-Rough 11/22/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 11/22/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/27/2023 Approved EUGENE CASSIDY
Insulation 11/27/2023 Approved EUGENE CASSIDY
Drywall Nailing 12/6/2023 Corrections Issued EUGENE CASSIDY
Drywall Nailing 1/8/2024 Approved JOHN KLARIN
Shower Pan 1/8/2024 Approved JOHN KLARIN
Interior/Exterior Lathing 1/19/2024 Partial Approval JAMES CHAVEZ
ELECTRICAL-Final 3/22/2024 Partial Approval EUGENE CASSIDY
Final 3/22/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 3/22/2024 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 3/22/2024 Approved EUGENE CASSIDY
PLUMBING-Final 3/22/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 3/22/2024 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 4/12/2024 Approved EUGENE CASSIDY
Final 4/12/2024 OK to Issue CofO EUGENE CASSIDY
Green Building Final 4/12/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Approved EUGENE CASSIDY
Service/Power Release 4/12/2024 Not Required EUGENE CASSIDY
Smoke Detectors 4/12/2024 Approved EUGENE CASSIDY