3886 S HARVARD BLVD 90062
Certificate Information: 3886 S HARVARD BLVD 90062
- Application / Permit
- 23014-10000-00988
- Plan Check / Job No.
- B23LA04597
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: SECOND FLOOR AND GARAGE ADDITION, INTERIOR AND EXTERIOR REMODEL TO (E) 1-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 8/9/2023
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | DANIEL YIP |
| Corrections Issued | 3/25/2023 | DANIEL YIP |
| Quality Review Completed | 3/29/2023 | GARO TELMI |
| Plan Check Approved | 5/8/2023 | DANIEL YIP |
| Issued | 8/9/2023 | APPLICANT |
| CofO in Progress | 9/4/2024 | SABAS ALONSO |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/25/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2023 | WALLIE JONG |
| Sewer availability | Cleared | 4/27/2023 | WALLIE JONG |
Contact Information
| Contractor | American Home Improvement Inc; Lic. No.: 835537-B | 20335 VENTURA BLVD #422 WOODLAND HILLS, CA 91364 |
| Engineer | Mezey,, Steven William; Lic. No.: NA2665 | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/13/2023 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 10/18/2023 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2023 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 11/9/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Corrections Issued | SABAS ALONSO |
| Deputy Wood Construction | 11/29/2023 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2023 | Approved | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 12/19/2023 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 12/21/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/21/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/8/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 1/19/2024 | Partial Approval | SABAS ALONSO |
| HVAC-Rough | 2/6/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Corrections Issued | SABAS ALONSO |
| Verify Sprinkler Sign Off | 2/15/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Conditional Approval | SABAS ALONSO |
| Green Building Rough | 3/5/2024 | Approved | SABAS ALONSO |
| Wood Frame | 3/5/2024 | Corrections Issued | SABAS ALONSO |
| Deputy Drilled-In Anchors | 3/7/2024 | Conditional Approval | SABAS ALONSO |
| Deputy Steel/Welding | 3/7/2024 | Conditional Approval | SABAS ALONSO |
| Shower Pan | 3/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Masonry Wall/Backfill | 3/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 3/18/2024 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/26/2024 | Approved | SABAS ALONSO |
| Insulation | 4/1/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/1/2024 | Approved | SABAS ALONSO |
| Shower Pan | 4/1/2024 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 4/19/2024 | Approved | SABAS ALONSO |
| Shower Pan | 4/23/2024 | Approved | SABAS ALONSO |
| Final | 8/6/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 8/6/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 8/6/2024 | Approved | SABAS ALONSO |
| Final | 8/27/2024 | Corrections Issued | SABAS ALONSO |
| Final | 9/3/2024 | OK to Issue CofO | SABAS ALONSO |