13109 W ROSE AVE 90066
Certificate Information: 13109 W ROSE AVE 90066
- Application / Permit
- 23014-10000-00985
- Plan Check / Job No.
- B23LA04575
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 715 SQFT ADU ADDITION ON EXISTING DETACHED GARAGE PER LAMC 12.22 A.33 (c)-(d) AND 228 SQFT ROOFTOP DECK ABOVE EXISTING GARAGE.
- Permit Issued
- Issued on 3/26/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2023 | ADAM HEGAZI |
| Corrections Issued | 3/23/2023 | ADAM HEGAZI |
| Building Plans Picked Up | 4/4/2023 | APPLICANT |
| Plan Check Approved | 3/26/2024 | SAMUEL GONZALEZ |
| Issued | 3/26/2024 | APPLICANT |
| CofO in Progress | 1/31/2025 | JESUS RODRIGUEZ |
| CofO in Progress | 2/5/2025 | JESUS RODRIGUEZ |
| CofO in Progress | 3/14/2025 | MICHAEL ALLEN |
| CofO Issued | 3/25/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/25/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/20/2023 | JASON NG |
| Specific Plan | Cleared | 6/27/2023 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 7/9/2023 | AHMED AMARRAGY |
| Low Impact Development (LID) | Cleared | 1/5/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 1/5/2024 | DARIN LAM |
Contact Information
| Contractor | Rolenconstruction Llc; Lic. No.: 1105889-B | 5250 LANKERSHIM BLVD 500 NORTH HOLLYWOOD, CA 91601 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/17/2024 | Partial Approval | JESUS RODRIGUEZ |
| Sewer | 4/17/2024 | Approved | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 4/22/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 4/23/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 5/21/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/21/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/10/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/13/2024 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 6/13/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 6/20/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 6/20/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 6/28/2024 | Approved | HERBERT GIRON |
| HVAC-Rough | 6/28/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 7/9/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 7/24/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 7/24/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 7/24/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/24/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/7/2024 | Partial Approval | JESUS PINEDA |
| Shower Pan | 8/7/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 8/8/2024 | Approved | DANIEL VERA |
| Drywall Nailing | 8/13/2024 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Approved | JESUS RODRIGUEZ |
| Final | 9/20/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 9/20/2024 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 9/20/2024 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 9/20/2024 | Corrections Issued | JESUS PINEDA |
| Final | 10/4/2024 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Final | 10/4/2024 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 10/4/2024 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 10/17/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 10/17/2024 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 10/25/2024 | SGSOV Not Ready | JESUS PINEDA |
| ELECTRICAL-Final | 10/28/2024 | Approved | JESUS PINEDA |
| Green Building Final | 10/28/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 10/28/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 10/28/2024 | Approved | JESUS PINEDA |
| Service/Power Release | 10/28/2024 | Not Ready for Inspection | JESUS PINEDA |
| Smoke Detectors | 10/28/2024 | Approved | JESUS PINEDA |
| Service/Power Release | 11/12/2024 | Approved | ARAM AVEDISIAN |
| Final | 11/21/2024 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 11/21/2024 | SGSOV Not Required | JESUS PINEDA |
| Final | 1/30/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 3/13/2025 | OK to Issue CofO | MICHAEL ALLEN |