3579-3579 1/2 E TACOMA AVE 90065
Certificate Information: 3579-3579 1/2 E TACOMA AVE 90065
- Application / Permit
- 23014-10000-00984
- Plan Check / Job No.
- B23LA04564
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED NEW 594.6 SQFT ADU IN EXISTING CRAWLSPACE OF EXISTING SFD PER LAMC 12.33A(c)(e). NEW 168.3 SF DECK OFFTHE NEW ADU.
- Permit Issued
- Issued on 7/7/2023
- Issuing Office
- Current Status
- CofO Corrected on 1/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | NGHI SU |
| Corrections Issued | 3/28/2023 | NGHI SU |
| Quality Review Completed | 3/30/2023 | KEN GILL |
| Plan Check Approved | 6/20/2023 | NGHI SU |
| Issued | 7/7/2023 | APPLICANT |
| CofO in Progress | 1/18/2024 | ALIZAH MAYAGOITIA |
| CofO Issued-Status Void | 1/21/2024 | DEROLD HAUFF |
| Permit Finaled-Status Void | 1/21/2024 | DEROLD HAUFF |
| Re-Activate Permit | 1/23/2024 | DEROLD HAUFF |
| Permit Finaled | 1/23/2024 | DEROLD HAUFF |
| CofO Corrected | 1/23/2024 | DEROLD HAUFF |
| Permit Finaled | 1/23/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 3/28/2023 | NGHI SU |
| Grading Pre-Inspection | Cleared | 3/28/2023 | NGHI SU |
| BHO/Hillside ordinance | Cleared | 4/14/2023 | CELINA MORENO |
| Address approval | Cleared | 4/20/2023 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 4/20/2023 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 4/20/2023 | CELINA MORENO |
| Sewer availability | Cleared | 4/20/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2023 | CELINA MORENO |
| Miscellaneous | Cleared | 6/5/2023 | MARITZA PRZEKOP |
| Hydrant and Access approval | Cleared | 6/9/2023 | MATTHEW CRAIG |
| ZI | Cleared | 6/9/2023 | PABLO ESTRADA |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 894 SANTA MARIA CIRCLE DUARTE, CA 91010 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Geologist | Carrle,, Conrad Henry; Lic. No.: EG2359 | 23128 WILDWOOD ROAD NEWHALL, CA 91321 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/21/2023 | Approved | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 8/23/2023 | Corrections Issued | OSVALDO PARAMO |
| Piling/Pier/Caisson | 8/24/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 8/31/2023 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/31/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 9/1/2023 | Conditional Approval | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 9/8/2023 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/8/2023 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 9/8/2023 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 9/25/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 9/26/2023 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/11/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 10/11/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 10/11/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 10/11/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 10/13/2023 | Approved | OSVALDO PARAMO |
| Wood Frame | 10/13/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 10/24/2023 | Approved | OSVALDO PARAMO |
| Wood Frame | 10/24/2023 | Conditional Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 10/25/2023 | Conditional Approval | OSVALDO PARAMO |
| Insulation | 10/31/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 11/7/2023 | Partial Approval | OSVALDO PARAMO |
| Shower Pan | 11/7/2023 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 11/13/2023 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 1/9/2024 | Approved | OSVALDO PARAMO |
| Final | 1/9/2024 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/9/2024 | Approved | OSVALDO PARAMO |
| Green Building Final | 1/9/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 1/9/2024 | Approved | OSVALDO PARAMO |
| Final | 1/12/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 1/17/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |