411 S 26TH ST 90402

Certificate Information: 411 S 26TH ST 90402

Application / Permit
23014-10000-00982
Plan Check / Job No.
B23LA04523
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
GROUND FLOOR 2 STORY ADDITION TO (E) SFD
Permit Issued
Issued on 6/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 CARLOS MONTES
Corrections Issued 3/18/2023 CARLOS MONTES
Quality Review Completed 3/23/2023 KEN GILL
Plan Check Approved 6/6/2023 CARLOS MONTES
Issued 6/7/2023 APPLICANT
CofO in Progress 4/1/2024 ARAM AVEDISIAN
Permit Finaled 4/3/2024 DANIEL ORRANTE
CofO Issued 4/3/2024 DANIEL ORRANTE
Permit Finaled 4/3/2024 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 4/12/2023 EDMOND LEE
Eng Process Fee Ord 176,300 Cleared 4/13/2023 WALLIE JONG
Roof/Waste drainage to street Cleared 4/14/2023 ANTHONY MAINEZ
Hold Cleared 4/30/2023 MARIA VENDIVIL
Specific Plan Cleared 5/3/2023 PEDRO AYALA
Low Impact Development (LID) Cleared 5/11/2023 ANTHONY VARGAS
Sewer availability Cleared 5/25/2023 ANTHONY MAINEZ

Contact Information

Contractor Design Equity; Lic. No.: 1087681-B 20130 ROCKPORT WAY      MALIBU, CA 90265
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/4/2023 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 8/4/2023 Not Ready for Inspection MEL KHACHATOURIAN
Sewer 8/4/2023 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 8/10/2023 Corrections Issued CLAYTON GRAHAM
Sewer 8/10/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Rough 8/14/2023 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 8/15/2023 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 10/24/2023 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 11/15/2023 Not Ready for Inspection BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Approved BEN MOLSTAD
HVAC-Rough 11/15/2023 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 12/1/2023 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 12/1/2023 Not Ready for Inspection BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 12/1/2023 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 12/1/2023 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 12/5/2023 Not Ready for Inspection BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 12/5/2023 Corrections Issued BEN MOLSTAD
HVAC-Rough 12/5/2023 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 12/5/2023 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 12/6/2023 Not Ready for Inspection BEN MOLSTAD
Deputy Wood Construction 12/6/2023 Approved BEN MOLSTAD
ELECTRICAL-Rough 12/6/2023 Not Ready for Inspection BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Partial Approval BEN MOLSTAD
Green Building Rough 12/6/2023 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 12/6/2023 Corrections Issued BEN MOLSTAD
Gas Test 12/7/2023 Approved BEN MOLSTAD
HVAC-Rough 12/7/2023 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 12/8/2023 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 12/8/2023 Approved BEN MOLSTAD
ELECTRICAL-Rough 12/11/2023 Corrections Issued BEN MOLSTAD
Final 12/11/2023 Corrections Issued BEN MOLSTAD
HVAC-Rough 12/11/2023 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 12/12/2023 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 12/12/2023 Corrections Issued BEN MOLSTAD
Green Building Rough 12/12/2023 Not Ready for Inspection BEN MOLSTAD
Interior/Exterior Lathing 12/12/2023 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 12/14/2023 Approved BEN MOLSTAD
HVAC-Rough 12/14/2023 Approved BEN MOLSTAD
Interior/Exterior Lathing 12/14/2023 Approved BEN MOLSTAD
BUILDING-Rough-Frame 12/15/2023 Approved BEN MOLSTAD
Green Building Rough 12/15/2023 Approved BEN MOLSTAD
Insulation 12/18/2023 Approved BEN MOLSTAD
Shower Pan 12/18/2023 Approved BEN MOLSTAD
Drywall Nailing 12/26/2023 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 12/26/2023 Approved KEVIN SARGSYAN
Drywall Nailing 12/27/2023 Approved BEN MOLSTAD
Service/Power Release 12/27/2023 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 3/6/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 3/18/2024 Approved EVAN COOPER
HVAC-Final 3/18/2024 Approved EVAN COOPER
PLUMBING-Final 3/26/2024 Corrections Issued HERBERT GIRON
Final 3/27/2024 Corrections Issued ARAM AVEDISIAN
Green Building Final 3/27/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/27/2024 SGSOV Not Ready ARAM AVEDISIAN
Service/Power Release 3/27/2024 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 3/27/2024 Approved ARAM AVEDISIAN
Gas Test 3/28/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 3/28/2024 Corrections Issued HERBERT GIRON
Final 3/30/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Final 3/30/2024 Off-Hour Fees Due
Gas Test 3/30/2024 Approved OGANES TARAKHCHYAN
Gas Test 3/30/2024 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 3/30/2024 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 3/30/2024 SGSOV Approved OGANES TARAKHCHYAN
Final 4/1/2024 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 4/1/2024 Approved ARAM AVEDISIAN