8116 S FORDHAM ROAD 90045

Certificate Information: 8116 S FORDHAM ROAD 90045

Application / Permit
23014-10000-00970
Plan Check / Job No.
B23LA04455
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN: 9' X 19'-4" ADDITION TO (E) 2-STORY SFD TO ENLARGE BEDROOM, ADD BATHROOM, ADD W.I.C, AND RELOCATE LAUNDRY.
Permit Issued
Issued on 3/30/2023
Issuing Office
Current Status
CofO Issued on 10/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2023 APPLICANT
Assigned to Plan Check Engineer 3/17/2023 LUISANGEL VALENZUELA
Corrections Issued 3/18/2023 LUISANGEL VALENZUELA
Plan Check Approved 3/29/2023 LUISANGEL VALENZUELA
Issued 3/30/2023 APPLICANT
CofO in Progress 10/20/2023 BOBBY KEY
Permit Finaled 10/24/2023 DANIEL ORRANTE
CofO Issued 10/24/2023 DANIEL ORRANTE
Permit Finaled 10/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/21/2023 DINAH GARIN
Specific Plan Cleared 3/22/2023 FREDDY GARCIA
Roof/Waste drainage to street Cleared 3/28/2023 JASON NG

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Kofler Consulting Inc; Lic. No.: 1022557-B       ,
Contractor Kofler Design Build; Lic. No.: 1022557-B       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/1/2023 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 5/9/2023 Partial Approval BOBBY KEY
Special/Order Compliance 5/9/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Partial Approval BOBBY KEY
Insulation 5/12/2023 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 6/14/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 6/14/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Corrections Issued BOBBY KEY
HVAC-Rough 6/14/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 6/14/2023 Approved BOBBY KEY
ELECTRICAL-Rough 6/20/2023 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Approved BOBBY KEY
HVAC-Rough 6/20/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 6/27/2023 Approved BOBBY KEY
Insulation 6/27/2023 Approved BOBBY KEY
Interior/Exterior Lathing 6/27/2023 Partial Approval BOBBY KEY
Drywall Nailing 7/3/2023 Approved BOBBY KEY
Interior/Exterior Lathing 7/3/2023 Approved BOBBY KEY
Shower Pan 7/3/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/5/2023 SGSOV Not Ready HERBERT GIRON
ELECTRICAL-Final 9/14/2023 Approved BOBBY KEY
Final 9/14/2023 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 9/14/2023 Approved BOBBY KEY
HVAC-Final 9/14/2023 Approved BOBBY KEY
PLUMBING-Final 9/14/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/14/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 9/14/2023 Approved BOBBY KEY
Final 10/20/2023 OK to Issue CofO BOBBY KEY